22050 W HART ST 91303
Certificate Information: 22050 W HART ST 91303
- Application / Permit
- 20014-20000-03691
- Plan Check / Job No.
- B20VN11225
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 22'-1" X 36'-4" TO AND CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 2/26/2021
- Issuing Office
- Current Status
- CofO Issued on 12/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2020 | SELLA BENYAMIN |
| Corrections Issued | 9/15/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 9/17/2020 | APPLICANT |
| Plan Check Approved | 2/5/2021 | SELLA BENYAMIN |
| Issued | 2/26/2021 | APPLICANT |
| CofO in Progress | 11/30/2021 | TROY SANDERS |
| Permit Finaled | 12/2/2021 | JOHN JANSON |
| CofO Issued | 12/2/2021 | JOHN JANSON |
| Permit Finaled | 12/2/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/2/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 10/7/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 11/3/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/2/2020 | ROBIN YAMADA |
| Roof/Waste drainage to street | Cleared | 12/10/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/13/2021 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 4/13/2021 | Partial Approval | TROY SANDERS |
| Pre-Inspection | 4/13/2021 | Approved | TROY SANDERS |
| Underground Mechanical | 4/13/2021 | Approved | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 4/20/2021 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 4/20/2021 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2021 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 6/4/2021 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 6/4/2021 | Approved | TROY SANDERS |
| Green Building Rough | 6/4/2021 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Rough | 6/4/2021 | Approved | TROY SANDERS |
| PLUMBING-Rough | 6/4/2021 | Approved | TROY SANDERS |
| Wood Frame | 6/4/2021 | Not Ready for Inspection | TROY SANDERS |
| Insulation | 6/21/2021 | Corrections Issued | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 6/21/2021 | Approved | ASHLEY THOMPSON |
| Shower Pan | 6/21/2021 | Not Ready for Inspection | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 6/23/2021 | Approved | TROY SANDERS |
| Green Building Rough | 6/23/2021 | Approved | TROY SANDERS |
| Insulation | 6/23/2021 | Approved | TROY SANDERS |
| Shower Pan | 6/23/2021 | Approved | TROY SANDERS |
| Drywall Nailing | 7/1/2021 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 7/1/2021 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Drywall Nailing | 7/7/2021 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 7/7/2021 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 8/2/2021 | Partial Approval | JEFFREY PARD |
| Sewer | 8/2/2021 | Approved | JEFFREY PARD |
| Underground Mechanical | 8/2/2021 | Approved | JEFFREY PARD |
| Final | 11/4/2021 | Corrections Issued | TROY SANDERS |
| Green Building Final | 11/4/2021 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 11/4/2021 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 11/4/2021 | Approved | TROY SANDERS |
| Final | 11/30/2021 | OK to Issue CofO | TROY SANDERS |