7905 N VANTAGE AVE 91605
Certificate Information: 7905 N VANTAGE AVE 91605
- Application / Permit
- 20014-20000-03685
- Plan Check / Job No.
- B20VN11201
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EXTEND (E) REC. ROOM AND ADD 2ND FLR FOR ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 8/29/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 10/13/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 10/22/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 10/30/2020 | APPLICANT |
| Applicant returned to address corrections | 8/10/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 8/29/2022 | MOHAMMAD ESMAILI |
| Issued | 8/29/2022 | APPLICANT |
| CofO in Progress | 7/10/2023 | MATTHEW NELSON |
| Permit Finaled | 7/21/2023 | DANIEL ORRANTE |
| CofO Issued | 7/21/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/21/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/9/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 5/8/2021 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 8/13/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 5/2/2022 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 6/3/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/7/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Sewer | 9/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 9/21/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 9/29/2022 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 10/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 11/1/2022 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 12/12/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 12/12/2022 | Approved | MATTHEW NELSON |
| Green Building Rough | 12/12/2022 | Approved | MATTHEW NELSON |
| HVAC-Rough | 12/12/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 12/12/2022 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 12/12/2022 | Approved | MATTHEW NELSON |
| Insulation | 12/19/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 1/3/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 1/20/2023 | Approved | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 2/3/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 2/8/2023 | Approved | MATTHEW NELSON |
| Final | 4/24/2023 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 4/24/2023 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 4/24/2023 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 4/24/2023 | Approved | MATTHEW NELSON |
| Final | 7/7/2023 | OK to Issue CofO | MATTHEW NELSON |