7905 N VANTAGE AVE 91605

Certificate Information: 7905 N VANTAGE AVE 91605

Application / Permit
20014-20000-03685
Plan Check / Job No.
B20VN11201
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXTEND (E) REC. ROOM AND ADD 2ND FLR FOR ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 8/29/2022
Issuing Office
Valley
Current Status
CofO Issued on 7/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2020 APPLICANT
Assigned to Plan Check Engineer 10/8/2020 MOHAMMAD ESMAILI
Corrections Issued 10/13/2020 MOHAMMAD ESMAILI
Quality Review Completed 10/22/2020 OMID HEDAYAT
Building Plans Picked Up 10/30/2020 APPLICANT
Applicant returned to address corrections 8/10/2022 MOHAMMAD ESMAILI
Plan Check Approved 8/29/2022 MOHAMMAD ESMAILI
Issued 8/29/2022 APPLICANT
CofO in Progress 7/10/2023 MATTHEW NELSON
Permit Finaled 7/21/2023 DANIEL ORRANTE
CofO Issued 7/21/2023 DANIEL ORRANTE
Permit Finaled 7/21/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/9/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 5/8/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 5/8/2021 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 8/13/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 5/2/2022 JOSE DUARTE-DIAZ
Construction near power lines Cleared 6/3/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/7/2022 Partial Approval CHRISTOPHER DELLEFIELD
Sewer 9/7/2022 Approved CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 9/21/2022 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 9/29/2022 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 10/5/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 10/21/2022 Partial Approval CHRISTOPHER DELLEFIELD
Deputy Wood Construction 11/1/2022 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 11/7/2022 Partial Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 12/12/2022 Approved MATTHEW NELSON
ELECTRICAL-Rough 12/12/2022 Approved MATTHEW NELSON
Green Building Rough 12/12/2022 Approved MATTHEW NELSON
HVAC-Rough 12/12/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 12/12/2022 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 12/12/2022 Approved MATTHEW NELSON
Insulation 12/19/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Drywall Nailing 1/3/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 1/20/2023 Approved MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 2/3/2023 Not Ready for Inspection JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 2/8/2023 Approved MATTHEW NELSON
Final 4/24/2023 Corrections Issued MATTHEW NELSON
Green Building Final 4/24/2023 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 4/24/2023 SGSOV Approved MATTHEW NELSON
Smoke Detectors 4/24/2023 Approved MATTHEW NELSON
Final 7/7/2023 OK to Issue CofO MATTHEW NELSON