14545 W LYLE ST 91342

Certificate Information: 14545 W LYLE ST 91342

Application / Permit
20014-20000-03682
Plan Check / Job No.
B20VN11190
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 24'X 24'-10" IRREGULAR SHAPE ON FIRST FLOOR AND 21'-10" X 24'-10" ON SECOND FLOOR TO AND CONVERT (E) GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 5/25/2021
Issuing Office
Current Status
CofO Issued on 11/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 SELLA BENYAMIN
Corrections Issued 10/5/2020 SELLA BENYAMIN
Quality Review Completed 10/6/2020 STEVEN KIM
Building Plans Picked Up 10/6/2020 APPLICANT
Plan Check Approved 5/5/2021 SELLA BENYAMIN
Issued 5/25/2021 APPLICANT
CofO in Progress 11/7/2025 KEVIN BERBERYAN
Permit Finaled 11/18/2025 RUBEN SALAS
CofO Issued 11/18/2025 RUBEN SALAS
Permit Finaled 11/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/1/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 12/3/2020 GUILLERMO PETRA
Hydrant and Access approval Cleared 12/4/2020 GILBERT URREA
Sewer availability Cleared 12/18/2020 GUILLERMO PETRA
Low Impact Development Cleared 4/8/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 5/6/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Ananian,, Vatche; Lic. No.: C79073 19528 VENTURA BLVD #374      TARZANA, CA 91356

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/16/2021 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 9/14/2021 Partial Inspection JOHN HAYES
Pre-Inspection 9/14/2021 Partial Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 9/30/2021 No Access for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 10/4/2021 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 10/13/2021 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 10/13/2021 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 10/18/2021 Approved JOHN HAYES
Deputy Drilled-In Anchors 10/19/2021 Conditional Approval JOHN HAYES
BUILDING-Rough-Frame 1/21/2022 Not Ready for Inspection JOHN HAYES
Green Building Rough 1/21/2022 Not Ready for Inspection JOHN HAYES
Wood Frame 1/31/2022 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 3/29/2022 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 9/9/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 9/9/2022 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/29/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 11/18/2022 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 11/18/2022 Partial Approval ARAM AVEDISIAN
Insulation 2/21/2023 Partial Approval MATTHEW NELSON
Insulation 2/22/2023 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 3/30/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 3/30/2023 Approved ARAM AVEDISIAN
Green Building Rough 3/30/2023 Approved ARAM AVEDISIAN
HVAC-Rough 3/30/2023 Approved ARAM AVEDISIAN
Insulation 3/30/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 3/30/2023 Approved ARAM AVEDISIAN
Drywall Nailing 4/7/2023 Approved ARAM AVEDISIAN
Shower Pan 4/7/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 7/11/2023 Approved RAUL OLAGI
ELECTRICAL-Final 11/13/2023 Not Ready for Inspection KEVIN BERBERYAN
Final 11/13/2023 Not Ready for Inspection KEVIN BERBERYAN
Footing/Foundation/Slab 11/13/2023 Approved KEVIN BERBERYAN
Green Building Final 11/13/2023 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 11/13/2023 SGSOV Not Ready KEVIN BERBERYAN
Service/Power Release 11/13/2023 Partial Inspection KEVIN BERBERYAN
Smoke Detectors 11/13/2023 Not Ready for Inspection KEVIN BERBERYAN
Service/Power Release 12/12/2023 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Final 9/9/2024 No Access for Inspection KEVIN BERBERYAN
Final 9/9/2024 No Access for Inspection KEVIN BERBERYAN
Gas Test 9/9/2024 No Access for Inspection KEVIN BERBERYAN
Green Building Final 9/9/2024 No Access for Inspection KEVIN BERBERYAN
HVAC-Final 9/9/2024 No Access for Inspection KEVIN BERBERYAN
PLUMBING-Final 9/9/2024 No Access for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 9/9/2024 SGSOV Not Ready KEVIN BERBERYAN
Service/Power Release 9/9/2024 No Access for Inspection KEVIN BERBERYAN
Smoke Detectors 9/9/2024 No Access for Inspection KEVIN BERBERYAN
ELECTRICAL-Final 9/12/2024 Not Ready for Inspection KEVIN BERBERYAN
Final 9/12/2024 Corrections Issued KEVIN BERBERYAN
Gas Test 9/12/2024 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Final 9/12/2024 Not Ready for Inspection KEVIN BERBERYAN
PLUMBING-Final 9/12/2024 Not Ready for Inspection KEVIN BERBERYAN
Service/Power Release 9/12/2024 Not Ready for Inspection KEVIN BERBERYAN
Smoke Detectors 9/12/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Final 9/2/2025 Approved KEVIN BERBERYAN
Final 9/2/2025 Corrections Issued KEVIN BERBERYAN
Gas Test 9/2/2025 Approved KEVIN BERBERYAN
Green Building Final 9/2/2025 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Final 9/2/2025 Approved KEVIN BERBERYAN
PLUMBING-Final 9/2/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 9/2/2025 SGSOV Approved KEVIN BERBERYAN
Service/Power Release 9/2/2025 Approved KEVIN BERBERYAN
Final 11/3/2025 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 11/3/2025 Approved KEVIN BERBERYAN