6628 N SATSUMA AVE 91606

Certificate Information: 6628 N SATSUMA AVE 91606

Application / Permit
20014-20000-03677
Plan Check / Job No.
B20VN11184
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 18'-6" X 14' TO AND CONVERT EXISTING 20' X 18'-1" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d); ADD 9'-5" X 7'-4" PORCH
Permit Issued
Issued on 2/19/2021
Issuing Office
Current Status
CofO Issued on 3/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 SELLA BENYAMIN
Corrections Issued 9/21/2020 SELLA BENYAMIN
Quality Review Completed 9/24/2020 STEVEN KIM
Building Plans Picked Up 9/28/2020 APPLICANT
Plan Check Approved 2/19/2021 SELLA BENYAMIN
Issued 2/19/2021 APPLICANT
CofO in Progress 2/8/2022 JACK KARGODORIAN
Permit Finaled 3/4/2022 MICHAEL SMITH
CofO Issued 3/4/2022 MICHAEL SMITH
Permit Finaled 3/4/2022 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 12/11/2020 RIDWAN HARDY
Address approval Cleared 12/24/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/28/2020 ADRIAN CASTRO
Sewer availability Cleared 12/28/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 2/4/2021 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 2/5/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/13/2021 Approved DANIEL DREW
PLUMBING-Rough 5/13/2021 Partial Approval DANIEL DREW
ELECTRICAL-Rough 6/15/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 6/15/2021 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 7/12/2021 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 7/12/2021 Approved DANIEL DREW
HVAC-Rough 7/12/2021 Approved DANIEL DREW
ELECTRICAL-Rough 7/22/2021 Approved DANIEL DREW
HVAC-Rough 7/22/2021 Approved DANIEL DREW
Interior/Exterior Lathing 7/22/2021 Partial Approval DANIEL DREW
PLUMBING-Rough 7/22/2021 Approved DANIEL DREW
Rough-Elec/Plmb/HVAC 7/22/2021 Approved DANIEL DREW
Insulation 8/11/2021 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 8/18/2021 Approved DANIEL DREW
Interior/Exterior Lathing 8/18/2021 Approved DANIEL DREW
Drywall Nailing 8/24/2021 Approved DANIEL DREW
Shower Pan 8/24/2021 Not Ready for Inspection DANIEL DREW
Shower Pan 8/26/2021 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 9/21/2021 Approved JENNIFER RABUCHIN
Pre-Inspection 9/21/2021 Approved JENNIFER RABUCHIN
Shower Pan 9/21/2021 Approved JENNIFER RABUCHIN
Gas Test 10/8/2021 Not Ready for Inspection GREGG CUMMINGS
Sewer 10/8/2021 Corrections Issued GREGG CUMMINGS
Gas Test 10/13/2021 Approved DANIEL DREW
Sewer 10/13/2021 Approved DANIEL DREW
Gas Test 10/20/2021 Corrections Issued DANIEL DREW
ELECTRICAL-Final 10/22/2021 Approved DANIEL DREW
PLUMBING-Final 10/22/2021 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 10/22/2021 SGSOV Approved DANIEL DREW
Smoke Detectors 10/22/2021 Approved DANIEL DREW
Gas Test 10/25/2021 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 11/10/2021 Approved DANIEL DREW
Green Building Final 11/10/2021 Approved DANIEL DREW
Green Building Rough 11/10/2021 Approved DANIEL DREW
Final 11/12/2021 Not Ready for Inspection DANIEL DREW
Final 12/2/2021 Corrections Issued MATT KELLERMAN
Final 12/17/2021 Corrections Issued DAVID MATSON
Final 1/18/2022 Corrections Issued DAVID MATSON
Final 2/8/2022 OK to Issue CofO JACK KARGODORIAN