5845 N LEMONA AVE 91411

Certificate Information: 5845 N LEMONA AVE 91411

Application / Permit
20014-20000-03676
Plan Check / Job No.
B20VN11182
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EXPAND (E) BEDROOM, BATHROOM, DINING & LIVING ROOM (IRR 29'-3" X 39'-2") TO (E) 1-STORY SFD W/ ATTACHED GARAGE; INTERIOR REMODEL
Permit Issued
Issued on 4/29/2021
Issuing Office
Current Status
CofO Issued on 3/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/4/2020 APPLICANT
Assigned to Plan Check Engineer 9/10/2020 NILOOFAR MEHRAIN
Corrections Issued 9/15/2020 NILOOFAR MEHRAIN
Quality Review Completed 9/15/2020 CHON CHIO KUO
Building Plans Picked Up 9/16/2020 APPLICANT
Applicant returned to address corrections 12/15/2020 NILOOFAR MEHRAIN
Applicant returned to address corrections 4/6/2021 NILOOFAR MEHRAIN
Plan Check Approved 4/18/2021 NILOOFAR MEHRAIN
Issued 4/29/2021 APPLICANT
CofO in Progress 12/30/2021 RICHARD DOCKUS
CofO Issued 3/5/2022 MICHAEL SMITH
Permit Finaled 3/5/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/21/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/21/2021 JOHN TRIANTAFYLLOS
CPC Cleared 1/25/2021 PABLO ESTRADA
Low Impact Development Cleared 3/29/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 4/5/2021 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng David; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/7/2021 Partial Approval CHARLES POWELL
PLUMBING-Rough 5/7/2021 Not Ready for Inspection CHARLES POWELL
PLUMBING-Rough 6/16/2021 Not Ready for Inspection MICHAEL PELHAM
Wood Frame 6/16/2021 Not Ready for Inspection MICHAEL PELHAM
BUILDING-Rough-Frame 7/26/2021 Partial Approval CHRISTOPHE COCHRAN
Deputy Wood Construction 7/26/2021 Conditional Approval WILLIAM KUEHN
Green Building Rough 7/26/2021 Approved CHRISTOPHE COCHRAN
Deputy Wood Construction 7/27/2021 Conditional Approval MICHAEL TEMPLE
Underground Mechanical 8/3/2021 Approved JOHN HAYES
BUILDING-Rough-Frame 8/5/2021 Corrections Issued MATTHEW NELSON
ELECTRICAL-Rough 8/5/2021 Approved MATTHEW NELSON
HVAC-Rough 8/5/2021 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 8/5/2021 Approved MATTHEW NELSON
BUILDING-Rough-Frame 8/11/2021 Approved JENNIFER RABUCHIN
HVAC-Rough 8/11/2021 Approved JENNIFER RABUCHIN
Insulation 8/16/2021 Approved AMY COLIN
Interior/Exterior Lathing 8/20/2021 Not Ready for Inspection AMY COLIN
Shower Pan 8/20/2021 Approved AMY COLIN
Drywall Nailing 8/23/2021 Approved RICHARD DOCKUS
Interior/Exterior Lathing 8/24/2021 Partial Approval RICHARD DOCKUS
Shower Pan 8/24/2021 Approved RICHARD DOCKUS
Interior/Exterior Lathing 9/2/2021 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 11/4/2021 Approved RICHARD DOCKUS
HVAC-Final 11/9/2021 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Final 11/9/2021 Not Ready for Inspection RICHARD DOCKUS
Gas Test 11/15/2021 Approved JENNIFER RABUCHIN
HVAC-Final 11/15/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 11/15/2021 Approved JENNIFER RABUCHIN
HVAC-Final 11/18/2021 Corrections Issued MICHAEL TEMPLE
HVAC-Final 11/24/2021 Approved RICHARD DOCKUS
Final 12/8/2021 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 12/8/2021 Approved RICHARD DOCKUS
Green Building Final 12/8/2021 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 12/8/2021 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 12/8/2021 Approved RICHARD DOCKUS
Final 12/29/2021 OK to Issue CofO RICHARD DOCKUS