5845 N LEMONA AVE 91411
Certificate Information: 5845 N LEMONA AVE 91411
- Application / Permit
- 20014-20000-03676
- Plan Check / Job No.
- B20VN11182
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXPAND (E) BEDROOM, BATHROOM, DINING & LIVING ROOM (IRR 29'-3" X 39'-2") TO (E) 1-STORY SFD W/ ATTACHED GARAGE; INTERIOR REMODEL
- Permit Issued
- Issued on 4/29/2021
- Issuing Office
- Current Status
- CofO Issued on 3/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 9/15/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 9/15/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 9/16/2020 | APPLICANT |
| Applicant returned to address corrections | 12/15/2020 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 4/6/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 4/18/2021 | NILOOFAR MEHRAIN |
| Issued | 4/29/2021 | APPLICANT |
| CofO in Progress | 12/30/2021 | RICHARD DOCKUS |
| CofO Issued | 3/5/2022 | MICHAEL SMITH |
| Permit Finaled | 3/5/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/21/2021 | JOHN TRIANTAFYLLOS |
| CPC | Cleared | 1/25/2021 | PABLO ESTRADA |
| Low Impact Development | Cleared | 3/29/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/5/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng David; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/7/2021 | Partial Approval | CHARLES POWELL |
| PLUMBING-Rough | 5/7/2021 | Not Ready for Inspection | CHARLES POWELL |
| PLUMBING-Rough | 6/16/2021 | Not Ready for Inspection | MICHAEL PELHAM |
| Wood Frame | 6/16/2021 | Not Ready for Inspection | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 7/26/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 7/26/2021 | Conditional Approval | WILLIAM KUEHN |
| Green Building Rough | 7/26/2021 | Approved | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 7/27/2021 | Conditional Approval | MICHAEL TEMPLE |
| Underground Mechanical | 8/3/2021 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 8/5/2021 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 8/5/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 8/5/2021 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 8/5/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/11/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 8/11/2021 | Approved | JENNIFER RABUCHIN |
| Insulation | 8/16/2021 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 8/20/2021 | Not Ready for Inspection | AMY COLIN |
| Shower Pan | 8/20/2021 | Approved | AMY COLIN |
| Drywall Nailing | 8/23/2021 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 8/24/2021 | Partial Approval | RICHARD DOCKUS |
| Shower Pan | 8/24/2021 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 9/2/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 11/4/2021 | Approved | RICHARD DOCKUS |
| HVAC-Final | 11/9/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Final | 11/9/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Gas Test | 11/15/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 11/15/2021 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 11/15/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 11/18/2021 | Corrections Issued | MICHAEL TEMPLE |
| HVAC-Final | 11/24/2021 | Approved | RICHARD DOCKUS |
| Final | 12/8/2021 | Corrections Issued | RICHARD DOCKUS |
| Footing/Foundation/Slab | 12/8/2021 | Approved | RICHARD DOCKUS |
| Green Building Final | 12/8/2021 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 12/8/2021 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 12/8/2021 | Approved | RICHARD DOCKUS |
| Final | 12/29/2021 | OK to Issue CofO | RICHARD DOCKUS |