5405 N CEDROS AVE 91411

Certificate Information: 5405 N CEDROS AVE 91411

Application / Permit
20014-20000-03640
Plan Check / Job No.
B20VN11050
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
6'-7" X 11'-6" ADDITION OF A FRONT ENTRY PORCH AND INTERIOR REMODEL OF KITCHEN, BEDROOM, WINDOWS AND DOORS CHANGEOUT TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/19/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2020 APPLICANT
Assigned to Plan Check Engineer 9/3/2020 RAHEL BEYENE
Corrections Issued 9/10/2020 RAHEL BEYENE
Plan Check Approved 10/5/2020 RAPHAEL ROSAS
Issued 10/19/2020 APPLICANT
CofO in Progress 3/23/2021 BRENDAN LOONEY
CofO Issued 12/18/2021 MICHAEL SMITH
Permit Finaled 12/18/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/24/2020 ABDULLAH SADOZAI
Roof/Waste drainage to street Cleared 9/24/2020 ABDULLAH SADOZAI
Sewer availability Cleared 9/24/2020 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/22/2020 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 11/6/2020 Partial Approval ARAM AVEDISIAN
Green Building Rough 11/6/2020 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Rough 11/6/2020 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 11/12/2020 Partial Approval DAVID MATSON
PLUMBING-Rough 11/12/2020 Approved DAVID MATSON
HVAC-Rough 11/23/2020 Approved DANIEL ORRANTE
Wood Frame 11/23/2020 Corrections Issued DANIEL ORRANTE
Wood Frame 12/31/2020 Partial Approval CHARLES POWELL
Wood Frame 1/5/2021 Approved MICHAEL SMITH
ELECTRICAL-Rough 1/7/2021 Approved CHARLES POWELL
Interior/Exterior Lathing 1/7/2021 Approved CHARLES POWELL
Shower Pan 1/7/2021 Approved CHARLES POWELL
Insulation 1/11/2021 Approved CHARLES POWELL
Drywall Nailing 1/15/2021 Approved JENNIFER RABUCHIN
Green Building Rough 1/15/2021 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/3/2021 Approved CHARLES POWELL
ELECTRICAL-Final 3/3/2021 Not Ready for Inspection CHARLES POWELL
Final 3/3/2021 Not Ready for Inspection CHARLES POWELL
Green Building Final 3/3/2021 Approved CHARLES POWELL
HVAC-Final 3/3/2021 Approved CHARLES POWELL
PLUMBING-Final 3/3/2021 Approved CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 3/3/2021 SGSOV Not Ready CHARLES POWELL
Smoke Detectors 3/3/2021 Approved CHARLES POWELL
ELECTRICAL-Final 3/19/2021 Approved BRENDAN LOONEY
Final 3/19/2021 OK to Issue CofO BRENDAN LOONEY
PLUMBING-Final 3/19/2021 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 3/19/2021 SGSOV Approved BRENDAN LOONEY