11501 W DELANO ST 91606

Certificate Information: 11501 W DELANO ST 91606

Application / Permit
20014-20000-03632
Plan Check / Job No.
B20VN11036
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
21' X 13'-8" IRREGULAR ADDITION TO (E) SFD FOR NEW BEDROOM. WORK PER ENGINEER.
Permit Issued
Issued on 4/8/2021
Issuing Office
Current Status
CofO Issued on 8/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2020 APPLICANT
Assigned to Plan Check Engineer 8/28/2020 ROSENDO MEDINA
Corrections Issued 8/31/2020 ROSENDO MEDINA
Applicant returned to address corrections 10/16/2020 ROSENDO MEDINA
Applicant returned to address corrections 3/15/2021 ROSENDO MEDINA
Plan Check Approved 3/23/2021 ROSENDO MEDINA
Issued 4/8/2021 APPLICANT
Building Plans Picked Up 4/12/2021 APPLICANT
CofO in Progress 8/11/2021 DANIEL DREW
Permit Finaled 8/13/2022 DANIEL ORRANTE
CofO Issued 8/13/2022 DANIEL ORRANTE
Permit Finaled 8/13/2022 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/6/2020 GUILLERMO PETRA
Sewer availability Cleared 11/6/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 11/9/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/27/2021 Conditional Approval DANIEL ORRANTE
Footing/Foundation/Slab 5/6/2021 Approved DANIEL DREW
Grading Pre-Inspection 5/6/2021 Approved DANIEL DREW
BUILDING-Rough-Frame 5/27/2021 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/27/2021 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 6/4/2021 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 6/4/2021 Approved MISAEL ESPARZA
HVAC-Rough 6/4/2021 Approved MISAEL ESPARZA
Wood Frame 6/4/2021 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 6/17/2021 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 6/24/2021 Approved DANIEL DREW
Interior/Exterior Lathing 6/24/2021 Approved DANIEL DREW
Insulation 6/29/2021 Approved MORRIS JACKSON
Drywall Nailing 7/6/2021 Approved MORRIS JACKSON
BUILDING-Rough-Frame 8/10/2021 Approved DANIEL DREW
ELECTRICAL-Final 8/10/2021 Approved DANIEL DREW
Final 8/10/2021 OK to Issue CofO DANIEL DREW
Green Building Final 8/10/2021 Approved DANIEL DREW
Green Building Rough 8/10/2021 Approved DANIEL DREW
HVAC-Final 8/10/2021 Approved DANIEL DREW
PLUMBING-Final 8/10/2021 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 8/10/2021 SGSOV Approved DANIEL DREW
Smoke Detectors 8/10/2021 Approved DANIEL DREW