1034 1/2-1036 1/2 S HI POINT ST 90035

Certificate Information: 1034 1/2-1036 1/2 S HI POINT ST 90035

Application / Permit
20014-20000-03626
Plan Check / Job No.
B20VN11015
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 10' X 24' ADDITION TO FIRST FLOOR OF (E) 2 STORY GAR/REC RM CONVERT AND CONVERT ENTIRE BUILDING INTO IRREGULAR SHAPED 31'-6" X 32'-1" TWO STORY (N) DETACHED (2) -ADUS PER GCS 65852.2(e)(1)(D)AND LAMC 12.22A33(c),(d) AND (g) ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/24/2021
Issuing Office
Current Status
CofO Issued on 7/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 CHON CHIO KUO
Corrections Issued 9/21/2020 CHON CHIO KUO
Quality Review Completed 9/22/2020 STEVEN KIM
Building Plans Picked Up 9/28/2020 APPLICANT
Applicant returned to address corrections 6/24/2021 CHON CHIO KUO
Applicant returned to address corrections 7/9/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 7/28/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 8/3/2021 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 8/10/2021 SEWADA ZADOORAN MILAGARDI
Issued 8/24/2021 APPLICANT
CofO in Progress 7/21/2022 JOSE AVILA
Permit Finaled 7/28/2022 DEROLD HAUFF
CofO Issued 7/28/2022 DEROLD HAUFF
Permit Finaled 7/28/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/5/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 10/5/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 10/6/2020 CECILIO NAVARRO
Sewer availability Cleared 10/6/2020 CECILIO NAVARRO
Hydrant and Access approval Cleared 11/3/2020 MATTHEW CRAIG
CPC Cleared 11/24/2020 DANIEL CORONADO
HPOZ Cleared 6/15/2021 JONATHAN KAPLAN
ZI Cleared 6/15/2021 JONATHAN KAPLAN
Miscellaneous Cleared 7/22/2021 ARMEN MEHRABIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Nazarians,, Harmick Edward; Lic. No.: C91232 9825 OSO AVE      CHATSWORTH, CA 91311

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/23/2021 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 2/25/2022 Not Ready for Inspection JOSE AVILA
METHANE-Barrier 2/25/2022 Not Ready for Inspection JOSE AVILA
METHANE-Subgrade 2/25/2022 Not Ready for Inspection JOSE AVILA
Underground Mechanical 2/25/2022 Approved JOSE AVILA
PLUMBING-Rough 3/3/2022 Not Ready for Inspection JOSE AVILA
SGSOV-Seismic Gas S/O Valve 3/3/2022 SGSOV Not Ready JOSE AVILA
Underground Mechanical 3/3/2022 Approved JOSE AVILA
Footing/Foundation/Slab 3/8/2022 Approved JOSE AVILA
METHANE-Barrier 3/8/2022 Approved JOSE AVILA
METHANE-Subgrade 3/8/2022 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/18/2022 Approved JOSE AVILA
PLUMBING-Rough 3/22/2022 Approved JOSE AVILA
ELECTRICAL-Rough 3/23/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 3/30/2022 Approved JOSE AVILA
HVAC-Rough 3/30/2022 Corrections Issued JOSE AVILA
HVAC-Rough 4/6/2022 Approved JOSE AVILA
METHANE-Rough 4/6/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 4/12/2022 Approved JOSE AVILA
Insulation 4/14/2022 Approved JOSE AVILA
Drywall Nailing 4/15/2022 Approved JOSE AVILA
Drywall Nailing 4/18/2022 Approved JOSE AVILA
Shower Pan 4/18/2022 Approved JOSE AVILA
Interior/Exterior Lathing 5/2/2022 Approved JOSE AVILA
PLUMBING-Final 6/27/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Final 7/5/2022 Corrections Issued JOSE AVILA
HVAC-Final 7/5/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 7/5/2022 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 7/14/2022 Approved JOSE AVILA
ELECTRICAL-Final 7/14/2022 Approved JOSE AVILA
Final 7/14/2022 Corrections Issued JOSE AVILA
Green Building Final 7/14/2022 Approved JOSE AVILA
Green Building Rough 7/14/2022 Approved JOSE AVILA
HVAC-Final 7/14/2022 Approved JOSE AVILA
PLUMBING-Final 7/14/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 7/14/2022 SGSOV Approved JOSE AVILA
Smoke Detectors 7/14/2022 Approved JOSE AVILA
Final 7/20/2022 OK to Issue CofO JOSE AVILA
Service/Power Release 7/20/2022 Approved JOSE AVILA
Service/Power Release 7/21/2022 Approved JOSE AVILA