7956-7958 N NOBLE AVE 91402

Certificate Information: 7956-7958 N NOBLE AVE 91402

Application / Permit
20014-20000-03616
Plan Check / Job No.
B20VN10994
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD (7'-5"x 10'-5") & CONVERT (E) ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK PER ENGINEER.
Permit Issued
Issued on 10/12/2020
Issuing Office
Current Status
CofO Issued on 9/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2020 APPLICANT
Assigned to Plan Check Engineer 8/28/2020 TROY DEGUZMAN
Corrections Issued 8/29/2020 TROY DEGUZMAN
Building Plans Picked Up 9/2/2020 APPLICANT
Plan Check Approved 10/12/2020 TROY DEGUZMAN
Issued 10/12/2020 APPLICANT
CofO in Progress 8/26/2022 GREGG CUMMINGS
CofO Issued 9/3/2022 MICHAEL SMITH
Permit Finaled 9/3/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/30/2020 ABDULLAH SADOZAI
Roof/Waste drainage to street Cleared 9/30/2020 ABDULLAH SADOZAI
Eng Process Fee Ord 176,300 Cleared 10/1/2020 ADRIAN CASTRO
Sewer availability Cleared 10/1/2020 ADRIAN CASTRO

Contact Information

Contractor Green Advisor Inc; Lic. No.: 1065856-B 7660 BEVERLY BLVD #167      LOS ANGELES, CA 90036
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/2/2020 Partial Approval GREGG CUMMINGS
Sewer 11/2/2020 Approved GREGG CUMMINGS
Footing/Foundation/Slab 12/4/2020 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 5/24/2021 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 5/24/2021 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 5/24/2021 Corrections Issued GREGG CUMMINGS
BUILDING-Rough-Frame 12/8/2021 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 12/8/2021 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 1/21/2022 Approved GREGG CUMMINGS
Green Building Rough 1/21/2022 Approved GREGG CUMMINGS
HVAC-Rough 1/21/2022 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 1/21/2022 Approved GREGG CUMMINGS
Interior/Exterior Lathing 2/15/2022 Approved WILLIAM WREN
Insulation 2/23/2022 Approved WILLIAM WREN
Drywall Nailing 3/7/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 8/1/2022 Approved GREGG CUMMINGS
Final 8/1/2022 Corrections Issued GREGG CUMMINGS
Green Building Final 8/1/2022 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 8/1/2022 SGSOV Not Ready GREGG CUMMINGS
Smoke Detectors 8/1/2022 Approved GREGG CUMMINGS
ELECTRICAL-Final 8/17/2022 Approved GREGG CUMMINGS
Final 8/17/2022 Corrections Issued GREGG CUMMINGS
HVAC-Final 8/17/2022 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 8/17/2022 SGSOV Approved GREGG CUMMINGS
Final 8/26/2022 OK to Issue CofO GREGG CUMMINGS
PLUMBING-Final 8/26/2022 Approved GREGG CUMMINGS