13053 W DICKENS ST 91604

Certificate Information: 13053 W DICKENS ST 91604

Application / Permit
20014-20000-03609
Plan Check / Job No.
B20VN10984
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ALL EXTERIOR AND INTERIOR WALLS OF AN EXISTING ONE STORY SINGLE FAMILY DWELLING EXCEPT FOR 13'-9" LF AT FRONT SIDE AND BUILD A 50'-0" x 81'-1" ONE STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE; NFPA-13D FIRE SPRINKLERS THROUGHOUT REQUIRED
Permit Issued
Issued on 4/7/2021
Issuing Office
Valley
Current Status
CofO Issued on 9/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 SEAN SHAHMIRI
Corrections Issued 9/23/2020 SEAN SHAHMIRI
Quality Review Completed 10/2/2020 OMID HEDAYAT
Building Plans Picked Up 10/6/2020 APPLICANT
Applicant returned to address corrections 3/1/2021 SEAN SHAHMIRI
Applicant returned to address corrections 3/9/2021 SEAN SHAHMIRI
Plan Check Approved 3/15/2021 SEAN SHAHMIRI
Applicant returned to address corrections 3/17/2021 SEAN SHAHMIRI
Issued 4/7/2021 APPLICANT
CofO in Progress 9/6/2022 CHRISTOPHE COCHRAN
Permit Finaled 9/6/2022 MICHAEL SMITH
CofO Issued 9/6/2022 MICHAEL SMITH
Permit Finaled 9/6/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/9/2020 GUILLERMO PETRA
Sewer availability Cleared 11/9/2020 GUILLERMO PETRA
ZI Cleared 12/2/2020 MIGUEL GAMBOA
Low Impact Development Cleared 12/21/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/23/2020 GUILLERMO PETRA
Hydrant and Access approval Cleared 1/30/2021 JEREMY CARTER
Miscellaneous Cleared 2/5/2021 MARKOS PEREZ-BRAN
Grading Pre-Inspection Cleared 3/1/2021 SEAN SHAHMIRI

Contact Information

Contractor Owner-Builder       ,
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/13/2021 Partial Inspection ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 4/26/2021 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 5/19/2021 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 5/19/2021 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 5/19/2021 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 5/25/2021 Partial Approval ARAM AVEDISIAN
Deputy Drilled-In Anchors 6/3/2021 Approved JUSTIN HAWLEY
Footing/Foundation/Slab 6/3/2021 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 6/8/2021 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/29/2021 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/12/2021 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 8/3/2021 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 8/9/2021 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 8/16/2021 Approved ARAM AVEDISIAN
PLUMBING-Rough 8/16/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 11/4/2021 Approved ARAM AVEDISIAN
Green Building Rough 11/4/2021 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 11/4/2021 Partial Approval ARAM AVEDISIAN
Drywall Nailing 11/12/2021 Approved ARAM AVEDISIAN
Insulation 11/12/2021 Approved ARAM AVEDISIAN
Shower Pan 12/27/2021 Corrections Issued GREGG CUMMINGS
Interior/Exterior Lathing 12/30/2021 Not Ready for Inspection THOMAS FINNILA
Shower Pan 12/30/2021 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 1/4/2022 Partial Approval CALEB MEISTER
Shower Pan 1/4/2022 Approved CALEB MEISTER
PLUMBING-Rough 4/25/2022 Partial Approval CALEB MEISTER
Sewer 4/25/2022 Approved CALEB MEISTER
Gas Test 7/1/2022 Approved CHRISTOPHE COCHRAN
HVAC-Final 7/1/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 7/1/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 7/20/2022 Approved CHRISTOPHE COCHRAN
Final 7/20/2022 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 7/20/2022 Approved CHRISTOPHE COCHRAN
Green Building Final 7/20/2022 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 7/20/2022 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 7/20/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 7/22/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Special/Order Compliance 8/18/2022 Approved CHRISTOPHE COCHRAN
Final 9/6/2022 OK to Issue CofO CHRISTOPHE COCHRAN
Service/Power Release 9/6/2022 Approved CHRISTOPHE COCHRAN