3958 N DIXIE CANYON AVE 91423

Certificate Information: 3958 N DIXIE CANYON AVE 91423

Application / Permit
20014-20000-03591
Plan Check / Job No.
B20VN10956
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, (N) IRREGULAR SHAPED 1ST 59'-8" X 29' ADDITION TO (E) SINGLE FAMILY ADDITION TO ADD (N) LIVING ROOM, REMODEL KITCHEN AND ATTACH (E) 20' X 20' GARAGE TO CREATE DECK ABOVE AND ATTACHED 7'X 4' TRELLIS ALL WORK PER ENGINNERING
Permit Issued
Issued on 5/2/2022
Issuing Office
Current Status
CofO Issued on 8/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 9/18/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 10/23/2020 OMID HEDAYAT
Building Plans Picked Up 11/13/2020 APPLICANT
Applicant returned to address corrections 12/3/2020 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 5/19/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 10/4/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 11/8/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 12/28/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 1/11/2022 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 2/9/2022 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 2/16/2022 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 3/30/2022 SEWADA ZADOORAN MILAGARDI
Issued 5/2/2022 APPLICANT
CofO in Progress 7/21/2025 CHRISTOPHE COCHRAN
Permit Finaled 8/18/2025 RUBEN SALAS
CofO Issued 8/18/2025 RUBEN SALAS
Permit Finaled 8/18/2025 RUBEN SALAS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/29/2021 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 4/29/2021 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 4/29/2021 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 4/29/2021 GABRIEL ROBLES
Watercourse Cleared 4/29/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 5/3/2021 GABRIEL ROBLES
Sewer availability Cleared 5/7/2021 GABRIEL ROBLES
Distance to fire station Cleared 6/21/2021 GILBERT URREA
Hydrant and Access approval Cleared 6/21/2021 GILBERT URREA
Low Impact Development Cleared 8/11/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 8/31/2021 GABRIEL ROBLES
GPI Written Notices Cleared 2/9/2022 SEWADA ZADOORAN MILAGARDI
Grading Pre-Inspection Cleared 2/9/2022 SEWADA ZADOORAN MILAGARDI
BHO/Hillside ordinance Cleared 4/14/2022 LEE GUILBEAUX

Contact Information

Architect Humphries,, Douglas S; Lic. No.: C25559 12122 HARTSOOK STREET      VALLEY VILLAGE, CA 91607
Contractor Wyner Garret Benjamin; Lic. No.: 539079-B 12944 GREENLEAF STREET      STUDIO CITY, CA 91604
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 8/26/2022 Corrections Issued CHRISTOPHE COCHRAN
Piling/Pier/Caisson 8/29/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 8/30/2022 Partial Approval CHRISTOPHE COCHRAN
Piling/Pier/Caisson 8/30/2022 Partial Approval CHRISTOPHE COCHRAN
Piling/Pier/Caisson 9/1/2022 Approved CHRISTOPHE COCHRAN
Piling/Pier/Caisson 9/7/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 10/11/2022 Partial Approval CHRISTOPHE COCHRAN
Underground Mechanical 10/11/2022 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 1/6/2023 Partial Approval CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 1/19/2023 Conditional Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 1/19/2023 Approved CHRISTOPHE COCHRAN
Structural Steel Frame 1/19/2023 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 9/6/2023 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 10/10/2023 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Rough 10/10/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Rough 10/10/2023 Approved CHRISTOPHE COCHRAN
HVAC-Rough 10/10/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 10/10/2023 Approved CHRISTOPHE COCHRAN
Structural Steel Frame 10/10/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Wood Frame 10/10/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 10/13/2023 Not Ready for Inspection JOHN COLEMAN
Wood Frame 10/13/2023 Not Ready for Inspection JOHN COLEMAN
ELECTRICAL-Rough 10/16/2023 Approved CHRISTOPHE COCHRAN
Wood Frame 10/16/2023 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 11/6/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 11/6/2023 Partial Approval CHRISTOPHE COCHRAN
Insulation 11/13/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 11/13/2023 Approved CHRISTOPHE COCHRAN
Drywall Nailing 11/20/2023 Not Ready for Inspection THOMAS FINNILA
Drywall Nailing 12/5/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/5/2023 Approved CHRISTOPHE COCHRAN
Shower Pan 12/5/2023 Approved CHRISTOPHE COCHRAN
Sewer 2/29/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Sewer 3/1/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Sewer 3/4/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 10/7/2024 Approved MATTHEW NELSON
Final 10/7/2024 Corrections Issued MATTHEW NELSON
Green Building Final 10/7/2024 Approved MATTHEW NELSON
HVAC-Final 10/7/2024 Approved MATTHEW NELSON
PLUMBING-Final 10/7/2024 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/7/2024 SGSOV Approved MATTHEW NELSON
Smoke Detectors 10/7/2024 Approved MATTHEW NELSON
Final 10/23/2024 Corrections Issued CHRISTOPHE COCHRAN
Final 12/10/2024 No Access for Inspection CHRISTOPHE COCHRAN
Final 12/19/2024 OK to Issue CofO CHRISTOPHE COCHRAN