4643 N VARNA AVE 91423
Certificate Information: 4643 N VARNA AVE 91423
- Application / Permit
- 20014-20000-03573
- Plan Check / Job No.
- B20VN10941
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 16'-1" x 8'-6" MASTER BATHROOM TO (E)MASTER BEDROOM AND CONVERT THE (E) BATHROOM INTO A (N) WALK IN CLOSET. 3'-0" x 17'-4" ROOF EXTENSION AT KITCHEN. INTERIOR REMODEL TO THE (E) KITCHEN, DINING ROOM AND FAMILY ROOM.--- "COMPLY WITH DEPARTMENT ORDER effective date 10/09/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 11/9/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2020 | SARKIS HARABEDIAN |
| Corrections Issued | 9/2/2020 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 10/14/2020 | SARKIS HARABEDIAN |
| Plan Check Approved | 10/28/2020 | SARKIS HARABEDIAN |
| Issued | 11/9/2020 | APPLICANT |
| CofO in Progress | 12/6/2021 | GORDON ZUBER |
| CofO in Progress | 12/6/2021 | GORDON ZUBER |
| CofO Issued | 12/17/2021 | DANIEL SANCHEZ |
| Permit Finaled | 12/17/2021 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/15/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 9/16/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JONATHAN FRANCHINI, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/21/2020 | Not Ready for Inspection | GORDON ZUBER |
| BUILDING-Rough-Frame | 12/29/2020 | Not Ready for Inspection | EDDY ARDESSI |
| Excavation/Setback/Form/Re-Bar | 12/29/2020 | Corrections Issued | EDDY ARDESSI |
| Footing/Foundation/Slab | 12/29/2020 | Corrections Issued | EDDY ARDESSI |
| Green Building Rough | 12/29/2020 | Not Ready for Inspection | EDDY ARDESSI |
| MERV13>=Rough | 12/29/2020 | Not Ready for Inspection | EDDY ARDESSI |
| Footing/Foundation/Slab | 1/21/2021 | Approved | GORDON ZUBER |
| PLUMBING-Rough | 2/8/2021 | Partial Approval | GORDON ZUBER |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2021 | Partial Inspection | GORDON ZUBER |
| Wood Frame | 3/17/2021 | Corrections Issued | GORDON ZUBER |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2021 | Approved | GORDON ZUBER |
| Rough-Elec/Plmb/HVAC | 4/28/2021 | Not Ready for Inspection | GORDON ZUBER |
| BUILDING-Rough-Frame | 4/29/2021 | Approved | GORDON ZUBER |
| Green Building Rough | 4/29/2021 | Approved | GORDON ZUBER |
| MERV13>=Rough | 4/29/2021 | Approved | GORDON ZUBER |
| Interior/Exterior Lathing | 5/14/2021 | Approved | GORDON ZUBER |
| Shower Pan | 5/14/2021 | Approved | GORDON ZUBER |
| Insulation | 5/25/2021 | Approved | GORDON ZUBER |
| Interior/Exterior Lathing | 7/1/2021 | Approved | GORDON ZUBER |
| Drywall Nailing | 11/23/2021 | Approved | GORDON ZUBER |
| ELECTRICAL-Final | 11/23/2021 | Not Ready for Inspection | GORDON ZUBER |
| Final | 11/23/2021 | Not Ready for Inspection | GORDON ZUBER |
| Gas Test | 11/23/2021 | Approved | GORDON ZUBER |
| Green Building Final | 11/23/2021 | Not Ready for Inspection | GORDON ZUBER |
| MERV13>=Final | 11/23/2021 | Not Ready for Inspection | GORDON ZUBER |
| PLUMBING-Final | 11/23/2021 | Not Ready for Inspection | GORDON ZUBER |
| SGSOV-Seismic Gas S/O Valve | 11/23/2021 | SGSOV Approved | GORDON ZUBER |
| Smoke Detectors | 11/23/2021 | Approved | GORDON ZUBER |
| Final | 12/6/2021 | OK to Issue CofO | GORDON ZUBER |
| Green Building Final | 12/6/2021 | Approved | GORDON ZUBER |
| MERV13>=Final | 12/6/2021 | Approved | GORDON ZUBER |