10600 N BAIRD AVE 91326

Certificate Information: 10600 N BAIRD AVE 91326

Application / Permit
20014-20000-03543
Plan Check / Job No.
B20VN10850
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
448 SQ. FT. ADDITION OF A FAMILY ROOM, LAUNDRY AND PANTRY TO THE (E) SFD.
Permit Issued
Issued on 4/12/2021
Issuing Office
Current Status
CofO Issued on 3/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2020 APPLICANT
Assigned to Plan Check Engineer 8/29/2020 AMIR DANAI
Corrections Issued 9/1/2020 AMIR DANAI
Applicant returned to address corrections 2/17/2021 LUISANGEL VALENZUELA
Plan Check Approved 3/3/2021 LUISANGEL VALENZUELA
Issued 4/12/2021 APPLICANT
Building Plans Picked Up 4/14/2021 APPLICANT
CofO in Progress 1/4/2022 JEFFREY PARD
Permit Finaled 3/11/2022 RONALD MYRICK
CofO Issued 3/11/2022 RONALD MYRICK
Permit Finaled 3/11/2022 RONALD MYRICK

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/14/2020 GABRIEL ROBLES
Sewer availability Cleared 9/14/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/15/2020 GABRIEL ROBLES
Low Impact Development Cleared 1/26/2021 SARAH YOUSSEF

Contact Information

Contractor Buono Construction; Lic. No.: 508466-B 18632 LIGGETT STREET      NORTHRIDGE, CA 91324
Engineer Baites,, Dana Lamont; Lic. No.: C32787 1070 LANDOVER CROSSING      SUWANEE, GA 30024

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 6/25/2021 Partial Approval JEFFREY PARD
PLUMBING-Rough 6/25/2021 Partial Approval JEFFREY PARD
Footing/Foundation/Slab 7/6/2021 Approved JEFFREY PARD
ELECTRICAL-Rough 8/12/2021 Approved JEFFREY PARD
PLUMBING-Rough 8/12/2021 Approved JEFFREY PARD
BUILDING-Rough-Frame 8/26/2021 Approved JEFFREY PARD
Green Building Rough 8/26/2021 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 8/26/2021 Approved JEFFREY PARD
Insulation 9/9/2021 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 9/9/2021 Approved DEANDRE HOFFMAN
Drywall Nailing 9/13/2021 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 10/12/2021 Approved JEFFREY PARD
Final 10/12/2021 OK to Issue CofO JEFFREY PARD
Green Building Final 10/12/2021 Approved JEFFREY PARD
Green Building Rough 10/12/2021 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 10/12/2021 SGSOV Approved JEFFREY PARD
Smoke Detectors 10/12/2021 Approved JEFFREY PARD
Special/Order Compliance 1/28/2022 Corrections Issued DAVID SCANTLIN