819 E ROSE AVE 90291

Certificate Information: 819 E ROSE AVE 90291

Application / Permit
20014-20000-03539
Plan Check / Job No.
B20VN10824
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE 1'-6" X 8'-4" PORTION OF GARAGE AND CONVERT REMAINING 17'-6" X 18' (E) DETACHED GARAGE AND ADD 28'-6" X 36'-2" IRREGULAR SHAPE TO CREATE A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/1/2021
Issuing Office
Current Status
CofO Issued on 4/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/20/2020 APPLICANT
Assigned to Plan Check Engineer 8/26/2020 RAPHAEL ROSAS
Corrections Issued 8/29/2020 RAPHAEL ROSAS
Plan Check Approved 2/9/2021 RAPHAEL ROSAS
Issued 4/1/2021 APPLICANT
CofO in Progress 4/11/2023 HERBERT GIRON
Permit Finaled 4/18/2023 DANIEL ORRANTE
CofO Issued 4/18/2023 DANIEL ORRANTE
Permit Finaled 4/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/13/2020 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 10/14/2020 SAUL GARCIA
Sewer availability Cleared 10/14/2020 SAUL GARCIA
Hydrant and Access approval Cleared 10/26/2020 KURT CORRAL
Specific Plan Cleared 11/5/2020 VALERIA CEJA
Low Impact Development Cleared 1/28/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 2/22/2021 TRACY TATE

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/25/2022 Approved JOHNNY MIRANDA
Underground Mechanical 3/14/2022 Partial Approval DAVID FEILER
PLUMBING-Rough 4/8/2022 Partial Approval DAVID FEILER
Sewer 4/8/2022 Approved DAVID FEILER
Deputy Drilled-In Anchors 4/15/2022 Approved MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 4/27/2022 Approved BOBBY KEY
Footing/Foundation/Slab 4/27/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 7/14/2022 Partial Approval DAVID FEILER
ELECTRICAL-Rough 7/14/2022 Corrections Issued DAVID FEILER
Green Building Rough 7/14/2022 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 7/14/2022 Approved DAVID FEILER
Underground Mechanical 7/14/2022 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 8/16/2022 Approved DAVID FEILER
ELECTRICAL-Rough 8/16/2022 Approved DAVID FEILER
Green Building Rough 8/16/2022 Approved DAVID FEILER
Insulation 8/23/2022 Approved DAVID FEILER
Interior/Exterior Lathing 8/23/2022 Partial Approval DAVID FEILER
Drywall Nailing 9/7/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 9/7/2022 Approved JESUS RODRIGUEZ
Shower Pan 9/7/2022 Approved JESUS RODRIGUEZ
Final 2/3/2023 Corrections Issued EVAN COOPER
Green Building Final 2/3/2023 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 2/3/2023 SGSOV Approved EVAN COOPER
Smoke Detectors 2/3/2023 Approved EVAN COOPER
ELECTRICAL-Final 4/5/2023 Corrections Issued HERBERT GIRON
Final 4/5/2023 Corrections Issued HERBERT GIRON
HVAC-Final 4/5/2023 Approved HERBERT GIRON
PLUMBING-Final 4/5/2023 Approved HERBERT GIRON
ELECTRICAL-Final 4/10/2023 Approved HERBERT GIRON
Final 4/10/2023 OK to Issue CofO HERBERT GIRON
Service/Power Release 4/10/2023 Approved HERBERT GIRON