12668 N COMETA AVE 91340
Certificate Information: 12668 N COMETA AVE 91340
- Application / Permit
- 20014-20000-03535
- Plan Check / Job No.
- B20VN10804
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX 18' X 10' DETACHED GARAGE INTO ACCESSORY DWELLING UNIT WITH 15'-5"X 10'ADDITION PER LAMC 12.22 A.33(c) AND (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 1/10/2022
- Issuing Office
- Current Status
- CofO Issued on 4/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 8/24/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 11/4/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 11/5/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 2/5/2021 | ROSENDO MEDINA |
| Applicant returned to address corrections | 7/4/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 12/3/2021 | DANIEL SANJUAN |
| Issued | 1/10/2022 | APPLICANT |
| Building Plans Picked Up | 1/21/2022 | APPLICANT |
| CofO in Progress | 4/17/2023 | ARAM AVEDISIAN |
| Permit Finaled | 4/18/2023 | MICHAEL SMITH |
| CofO Issued | 4/18/2023 | MICHAEL SMITH |
| Permit Finaled | 4/18/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/25/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 8/25/2020 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 10/13/2020 | MANUEL TEJADA |
| Sewer availability | Cleared | 10/26/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Badilla, Garces, Maria Elena; Lic. No.: C81817 | 3505 S WHITINGHAM DR WEST COVINA, CA 91792 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/10/2022 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 4/6/2022 | Approved | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 7/20/2022 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2022 | Partial Approval | WILLIAM WREN |
| PLUMBING-Rough | 8/5/2022 | Partial Approval | WILLIAM WREN |
| ELECTRICAL-Rough | 9/6/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/6/2022 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 10/17/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 10/24/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 11/3/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/3/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 11/3/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 11/3/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 11/3/2022 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 11/10/2022 | Approved | ARAM AVEDISIAN |
| Final | 4/3/2023 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 4/3/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 4/3/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 4/3/2023 | Approved | ARAM AVEDISIAN |
| Final | 4/12/2023 | Corrections Issued | ARAM AVEDISIAN |
| Final | 4/17/2023 | OK to Issue CofO | ARAM AVEDISIAN |