331 S BEVERLY GLEN BLVD 90024
Certificate Information: 331 S BEVERLY GLEN BLVD 90024
- Application / Permit
- 20014-20000-03528
- Plan Check / Job No.
- B20VN10781
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT AND ADDITION (38'-2"X27'-7") PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 1/20/2021
- Issuing Office
- Current Status
- CofO Issued on 6/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 9/15/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 10/2/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 10/2/2020 | APPLICANT |
| Plan Check Approved | 1/20/2021 | MOHAMMAD ESMAILI |
| Issued | 1/20/2021 | APPLICANT |
| CofO in Progress | 6/8/2023 | STEPHANIE SWANSON |
| Permit Finaled | 6/9/2023 | DANIEL ORRANTE |
| CofO Issued | 6/9/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/9/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 11/18/2020 | DENZEL HENDERSON |
| ZI | Cleared | 11/18/2020 | DENZEL HENDERSON |
| Address approval | Cleared | 11/30/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 11/30/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2020 | DINAH GARIN |
| Sewer availability | Cleared | 12/1/2020 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 12/11/2020 | PATRICK MISCHLICH |
Contact Information
| Architect | Grant,, Cynthia L; Lic. No.: C27260 | 14971 SUTTON ST SHERMAN OAKS, CA 91403 |
| Contractor | Aron Builders Inc; Lic. No.: 651900-B | P O BOX 1800 AGOURA HILLS, CA 91376 |
| Engineer | Resnick,, Bruce Daniel; Lic. No.: S3293 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/11/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 3/11/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Deputy Steel/Welding | 2/17/2022 | Conditional Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2022 | Corrections Issued | BRENDAN LOONEY |
| Sewer | 3/29/2022 | Partial Approval | BRENDAN LOONEY |
| Sewer | 3/31/2022 | Approved | BRENDAN LOONEY |
| Deputy Wood Construction | 5/24/2022 | Conditional Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2022 | Partial Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2022 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 12/5/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 12/5/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Wood Frame | 12/5/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 1/11/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/11/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Rough | 1/11/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/11/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 1/17/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 1/17/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 1/17/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 1/17/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 1/17/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 1/20/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 1/20/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 1/20/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 1/25/2023 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 3/21/2023 | Approved | CHRISTOPHER WILSON |
| Shower Pan | 3/21/2023 | Approved | CHRISTOPHER WILSON |
| Final | 5/18/2023 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 5/18/2023 | Approved | BRENDAN LOONEY |
| Green Building Final | 5/18/2023 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 5/18/2023 | SGSOV Approved | BRENDAN LOONEY |
| Smoke Detectors | 5/18/2023 | Approved | BRENDAN LOONEY |
| Final | 5/24/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 6/8/2023 | OK to Issue CofO | STEPHANIE SWANSON |