13368 W RELIANCE ST 91331
Certificate Information: 13368 W RELIANCE ST 91331
- Application / Permit
- 20014-20000-03524
- Plan Check / Job No.
- B20VN10771
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR ADDITION AND REMODEL TO (E) SFD (27'-7"X27'-11") 722 sq-ft ;Fire sprinkler nfpa13d
- Permit Issued
- Issued on 10/28/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 9/24/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 10/7/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 11/4/2020 | APPLICANT |
| Plan Check Approved | 10/26/2022 | MOHAMMAD ESMAILI |
| Issued | 10/28/2022 | APPLICANT |
| CofO in Progress | 2/28/2026 | MICHAEL PELHAM |
| Permit Finaled | 2/28/2026 | MICHAEL PELHAM |
| CofO Issued | 2/28/2026 | MICHAEL PELHAM |
| Permit Finaled | 2/28/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/14/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/13/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 6/9/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 6/22/2022 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 6/22/2022 | JOSE DUARTE-DIAZ |
| Public Works-Open Permits | Cleared | 6/22/2022 | JOSE DUARTE-DIAZ |
| Public Works-Sewers | Cleared | 6/22/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moreno,, Hector M; Lic. No.: C66015 | 1430 E COOLEY DR SUITE 120 COLTON, CA 92324 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 2/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 2/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 2/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 2/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 2/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/7/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 2/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 2/21/2023 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 3/9/2023 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 4/25/2023 | Partial Approval | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 5/4/2023 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 5/9/2023 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 6/28/2023 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 6/28/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 7/26/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 7/26/2023 | Corrections Issued | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 8/2/2023 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 8/4/2023 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 8/4/2023 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2023 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 8/4/2023 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Partial Approval | GREGG CUMMINGS |
| Insulation | 8/10/2023 | Partial Approval | GREGG CUMMINGS |
| Drywall Nailing | 8/16/2023 | Approved | KEVIN BERBERYAN |
| Pre-Inspection | 8/22/2023 | Approved | GREGG CUMMINGS |
| Wood Frame | 8/25/2023 | Corrections Issued | MISAEL ESPARZA |
| Pre-Inspection | 8/30/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/2/2023 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2023 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 10/2/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 10/2/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/11/2023 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/11/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 12/11/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/27/2023 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 12/27/2023 | Approved | GREGG CUMMINGS |
| Insulation | 12/27/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/27/2023 | Approved | GREGG CUMMINGS |
| Final | 3/12/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 3/12/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 3/12/2024 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 3/12/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 4/21/2025 | Approved | VINCENT HANLEY |
| Final | 4/21/2025 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 4/21/2025 | Approved | VINCENT HANLEY |
| Smoke Detectors | 4/21/2025 | Approved | VINCENT HANLEY |
| Final | 2/28/2026 | OK to Issue CofO | MICHAEL PELHAM |