17516 W CHASE ST 91325

Certificate Information: 17516 W CHASE ST 91325

Application / Permit
20014-20000-03504
Plan Check / Job No.
B20VN10713
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION ( 21.5FT X 18 FT, 375 SQFT) AND A REMODEL TO (E) ONE STORY SFD.
Permit Issued
Issued on 12/2/2020
Issuing Office
Current Status
CofO Issued on 4/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/19/2020 APPLICANT
Assigned to Plan Check Engineer 8/21/2020 TSE MING HUANG
Corrections Issued 8/25/2020 TSE MING HUANG
Plan Check Approved 9/22/2020 RICHARD GARCIA
Issued 12/2/2020 APPLICANT
CofO in Progress 4/16/2024 JAVIER RAMOS JR
Permit Finaled 4/24/2024 RUBEN SALAS
CofO Issued 4/24/2024 RUBEN SALAS
Permit Finaled 4/24/2024 RUBEN SALAS

Permit Application Clearance Information

ZI Cleared 9/10/2020 SHEILA GERSHON
Eng Process Fee Ord 176,300 Cleared 9/11/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 9/11/2020 ADRIAN CASTRO
Sewer availability Cleared 9/11/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/7/2021 Corrections Issued MARK JOHNSON
Deputy Drilled-In Anchors 5/17/2021 No Access for Inspection MARK JOHNSON
Footing/Foundation/Slab 5/21/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 7/28/2021 Partial Approval MARK JOHNSON
Green Building Rough 7/28/2021 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Rough 10/7/2021 Approved MARK JOHNSON
HVAC-Rough 10/7/2021 Approved MARK JOHNSON
PLUMBING-Rough 10/7/2021 Partial Approval MARK JOHNSON
Rough-Elec/Plmb/HVAC 10/7/2021 Not Ready for Inspection MARK JOHNSON
Wood Frame 10/7/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 10/14/2021 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 11/2/2021 Approved DANIEL DREW
Green Building Rough 11/2/2021 Approved DANIEL DREW
Insulation 11/2/2021 Approved DANIEL DREW
Drywall Nailing 11/24/2021 Approved MARK JOHNSON
PLUMBING-Rough 1/5/2022 Approved MARK JOHNSON
Shower Pan 1/5/2022 Approved MARK JOHNSON
Interior/Exterior Lathing 1/20/2022 Approved JESUS RODRIGUEZ
Final 8/10/2022 Corrections Issued JAVIER RAMOS JR
Green Building Final 8/10/2022 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/10/2022 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 8/10/2022 Approved JAVIER RAMOS JR
Final 4/16/2024 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 4/16/2024 Approved JAVIER RAMOS JR