8155 W BEVERLY BLVD 90048
Certificate Information: 8155 W BEVERLY BLVD 90048
- Application / Permit
- 20014-20000-03499
- Plan Check / Job No.
- B20VN10701
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Office
- Work Description
- RAISE PORTION OF (11'-10" X 19'-8") ROOF FOR (N) ATRIUM ON 2ND FLOOR OF (E) 2-STORY MEDICAL & NON-MEDICAL OFFICES; INTERIOR REMODEL
- Permit Issued
- Issued on 10/18/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 9/4/2020 | APPLICANT |
| Green Plans Picked Up | 9/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 9/17/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 9/17/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 9/22/2020 | APPLICANT |
| Applicant returned to address corrections | 6/1/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 9/1/2021 | NILOOFAR MEHRAIN |
| Issued | 10/18/2021 | APPLICANT |
| CofO in Progress | 9/8/2023 | ERNESTO CORRAL |
| CofO Issued | 9/15/2023 | TED RIES |
| Permit Finaled | 9/15/2023 | TED RIES |
Permit Application Clearance Information
| Green Code | Cleared | 1/26/2021 | AARON COSTA |
| Hydrant and Access approval | Cleared | 5/14/2021 | JOHN CONNEALLY |
| Comm Cor/Mini-Mall | Cleared | 5/26/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 5/26/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 5/26/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 5/26/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 5/26/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 5/26/2021 | MIGUEL GAMBOA |
| ZA Case | Cleared | 5/26/2021 | MIGUEL GAMBOA |
| DAS Clearance | Cleared | 8/19/2021 | NILOOFAR MEHRAIN |
| Highway dedication | Cleared | 9/24/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 9/24/2021 | JEANIE LAM |
| Sewer availability | Cleared | 9/24/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/27/2021 | JEANIE LAM |
Contact Information
| Contractor | Essential Construction; Lic. No.: 680963-B | 5318B CANOGA AVE WOODLAND HILLS, CA 91364 |
| Engineer | Villafana,, Donald Eugene; Lic. No.: C37354 | 1050 STERN LANE OXNARD, CA 93030 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/26/2022 | Approved | SORIN CIRSTOIU |
| METHANE-Barrier | 5/26/2022 | Approved | SORIN CIRSTOIU |
| METHANE-Subgrade | 5/26/2022 | Approved | SORIN CIRSTOIU |
| Deputy Reinf. Concrete | 6/8/2022 | Conditional Approval | ERNESTO CORRAL |
| Green Building Rough | 12/14/2022 | Not Ready for Inspection | RONALD JIMENEZ |
| METHANE-Rough | 12/14/2022 | Approved | RONALD JIMENEZ |
| Wood Frame | 12/14/2022 | Corrections Issued | RONALD JIMENEZ |
| Green Building Rough | 1/23/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 1/23/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Rough | 2/23/2023 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 2/23/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 4/11/2023 | Approved | VAHE KELEDJIAN |
| Green Building Rough | 4/21/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 4/21/2023 | Partial Approval | JEROME BLACKWOOD |
| Final | 7/18/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Final | 7/18/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Rough | 7/18/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 7/18/2023 | SGSOV Approved | JEROME BLACKWOOD |
| Smoke Detectors | 7/18/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 7/18/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Final | 8/17/2023 | Partial Inspection | JEROME BLACKWOOD |
| Green Building Final | 8/17/2023 | Approved | JEROME BLACKWOOD |
| Green Building Rough | 8/17/2023 | Approved | JEROME BLACKWOOD |
| Smoke Detectors | 8/17/2023 | Approved | JEROME BLACKWOOD |
| Wood Frame | 8/17/2023 | Partial Approval | JEROME BLACKWOOD |
| Final | 9/6/2023 | Partial Inspection | JEROME BLACKWOOD |
| Wood Frame | 9/7/2023 | Approved | RAFAEL CORTES |
| Final | 9/8/2023 | OK to Issue CofO | JEROME BLACKWOOD |