2049 1/2 N SICHEL ST 90031

Certificate Information: 2049 1/2 N SICHEL ST 90031

Application / Permit
20014-20000-03487
Plan Check / Job No.
B20VN10656
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 19'-7" x 27'-0" IRREGULAR SHAPED FIRST FLOOR ADDITION WITH 4'-0" x 14'-0" PORCH AND 19'-7" x 28'-0" SECOND FLOOR ADDITION TO (E) DETACHED 1-CAR GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 6/2/2021
Issuing Office
Current Status
CofO Issued on 4/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/17/2020 APPLICANT
Assigned to Plan Check Engineer 9/10/2020 SARKIS HARABEDIAN
Corrections Issued 9/12/2020 SARKIS HARABEDIAN
Quality Review Completed 9/18/2020 STEVEN KIM
Applicant returned to address corrections 3/23/2021 SARKIS HARABEDIAN
Plan Check Approved 5/25/2021 SARKIS HARABEDIAN
Issued 6/2/2021 APPLICANT
Building Plans Picked Up 6/4/2021 APPLICANT
CofO in Progress 3/18/2023 OSVALDO PARAMO
CofO in Progress 3/18/2023 OSVALDO PARAMO
Permit Finaled 4/2/2023 DEROLD HAUFF
CofO Issued 4/2/2023 DEROLD HAUFF
Permit Finaled 4/2/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/22/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/22/2020 WALLIE JONG
Sewer availability Cleared 9/22/2020 WALLIE JONG
Low Impact Development Cleared 1/15/2021 SARAH YOUSSEF
Hydrant and Access approval Cleared 1/21/2021 MATTHEW CRAIG
Construction near power lines Cleared 1/29/2021 RIDWAN HARDY
Construction within easement Cleared 1/29/2021 RIDWAN HARDY
Roof/Waste drainage to street Cleared 2/9/2021 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Kator,, Khaled; Lic. No.: C69781 19519 TULSA ST      NORTHRIDGE, CA 91326

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/15/2022 Approved OSVALDO PARAMO
PLUMBING-Rough 2/15/2022 Partial Approval OSVALDO PARAMO
Deputy Drilled-In Anchors 2/16/2022 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 2/18/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 2/25/2022 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 2/25/2022 Partial Inspection OSVALDO PARAMO
Green Building Rough 2/25/2022 Not Ready for Inspection OSVALDO PARAMO
MERV13>=Rough 2/25/2022 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 3/3/2022 Partial Approval OSVALDO PARAMO
ELECTRICAL-Rough 3/4/2022 Approved OSVALDO PARAMO
HVAC-Rough 3/4/2022 Corrections Issued OSVALDO PARAMO
HVAC-Rough 3/9/2022 Approved OSVALDO PARAMO
PLUMBING-Rough 3/9/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 3/10/2022 Approved OSVALDO PARAMO
Green Building Rough 3/10/2022 Approved OSVALDO PARAMO
MERV13>=Rough 3/10/2022 Approved OSVALDO PARAMO
Insulation 3/17/2022 Approved OSVALDO PARAMO
Insulation 3/18/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 3/18/2022 Partial Approval OSVALDO PARAMO
Drywall Nailing 3/21/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 3/21/2022 Approved OSVALDO PARAMO
ELECTRICAL-Final 5/12/2022 Approved OSVALDO PARAMO
PLUMBING-Final 5/12/2022 Approved OSVALDO PARAMO
Final 6/17/2022 Corrections Issued OSVALDO PARAMO
Green Building Final 6/17/2022 Approved OSVALDO PARAMO
HVAC-Final 6/17/2022 Approved OSVALDO PARAMO
MERV13>=Final 6/17/2022 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 6/17/2022 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 6/17/2022 Approved OSVALDO PARAMO
Final 3/2/2023 Not Ready for Inspection JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 3/2/2023 SGSOV Approved JEFFREY MEAD
Final 3/15/2023 OK to Issue CofO OSVALDO PARAMO