5245 E HUB ST 90042

Certificate Information: 5245 E HUB ST 90042

Application / Permit
20014-20000-03483
Plan Check / Job No.
B20VN10637
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INT. REMODEL AND ADDITION TO (E) SFD. NFPA-13D FIRE SPRINKLERS.
Permit Issued
Issued on 6/10/2021
Issuing Office
Current Status
CofO Issued on 10/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 RODNEY SAMIIAN
Corrections Issued 9/24/2020 RODNEY SAMIIAN
Quality Review Completed 9/28/2020 CHON CHIO KUO
Building Plans Picked Up 9/29/2020 APPLICANT
Applicant returned to address corrections 2/9/2021 CHON CHIO KUO
Plan Check Approved 2/9/2021 CHON CHIO KUO
No Progress 2/9/2021 CHON CHIO KUO
Plan Check Approved 6/3/2021 CHON CHIO KUO
Issued 6/10/2021 APPLICANT
CofO in Progress 9/22/2022 HAMIK HARTOUNIAN
Permit Finaled 10/1/2022 DEROLD HAUFF
CofO Issued 10/1/2022 DEROLD HAUFF
Permit Finaled 10/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 11/20/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 11/30/2020 WALLIE JONG
Low Impact Development Cleared 12/14/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 12/15/2020 WALLIE JONG
Hydrant and Access approval Cleared 1/12/2021 JEREMY CARTER

Contact Information

Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/16/2021 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 6/16/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 6/16/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 6/22/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Piling/Pier/Caisson 6/22/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/24/2021 Corrections Issued HAMIK HARTOUNIAN
Pre-Inspection 6/24/2021 Partial Inspection ALAN MORELOS
Excavation/Setback/Form/Re-Bar 6/28/2021 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/30/2021 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 7/2/2021 Partial Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 7/26/2021 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/27/2021 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 8/2/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 8/2/2021 Partial Approval HAMIK HARTOUNIAN
Underground Mechanical 8/3/2021 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/5/2021 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/4/2021 Corrections Issued BRAD BESCOS
ELECTRICAL-Rough 10/4/2021 Approved BRAD BESCOS
Green Building Rough 10/4/2021 Not Ready for Inspection BRAD BESCOS
HVAC-Rough 10/4/2021 Approved BRAD BESCOS
PLUMBING-Rough 10/4/2021 Corrections Issued BRAD BESCOS
Verify Sprinkler Sign Off 10/4/2021 Not Ready for Inspection BRAD BESCOS
Floor/Roof Diaphrgm/Shear Wall 10/18/2021 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 10/18/2021 Conditional Approval HAMIK HARTOUNIAN
Special/Order Compliance 10/18/2021 Partial Inspection AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 10/22/2021 Partial Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/15/2021 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 11/15/2021 Approved HAMIK HARTOUNIAN
Sewer 11/15/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/19/2021 Partial Approval HAMIK HARTOUNIAN
Shower Pan 11/19/2021 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/22/2021 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 11/24/2021 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 11/24/2021 Approved HAMIK HARTOUNIAN
Sewer 11/24/2021 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 11/24/2021 Approved HAMIK HARTOUNIAN
Insulation 12/1/2021 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/9/2022 Corrections Issued HAMIK HARTOUNIAN
Drywall Nailing 6/9/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Final 6/9/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Final 6/9/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 6/9/2022 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Final 6/9/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Final 6/9/2022 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 6/9/2022 SGSOV Not Ready HAMIK HARTOUNIAN
Service/Power Release 6/9/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Smoke Detectors 6/9/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 8/3/2022 Approved HAMIK HARTOUNIAN
Drywall Nailing 8/3/2022 Approved HAMIK HARTOUNIAN
Final 8/3/2022 Partial Inspection HAMIK HARTOUNIAN
Green Building Final 8/3/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/3/2022 SGSOV Approved HAMIK HARTOUNIAN
Final 9/22/2022 OK to Issue CofO HAMIK HARTOUNIAN