18241 W JOVAN ST 91335

Certificate Information: 18241 W JOVAN ST 91335

Application / Permit
20014-20000-03477
Plan Check / Job No.
B20VN10614
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 17'3" X 25'2" IRREGULAR SHAPED ADDITION TO THE (E) SFD TO CREATE NEW MASTER BEDROOM AND MASTER BATHROOM , ALL WORK PER ENGINEERING
Permit Issued
Issued on 10/23/2020
Issuing Office
Current Status
CofO Issued on 7/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/17/2020 APPLICANT
Assigned to Plan Check Engineer 8/21/2020 RAHEL BEYENE
Corrections Issued 9/2/2020 RAHEL BEYENE
Applicant returned to address corrections 10/4/2020 RICHARD GARCIA
Plan Check Approved 10/23/2020 RARES BODEA
Issued 10/23/2020 APPLICANT
CofO in Progress 7/6/2021 MICHAEL PELHAM
Permit Finaled 7/6/2021 MICHAEL SMITH
CofO Issued 7/6/2021 MICHAEL SMITH
Permit Finaled 7/6/2021 MICHAEL SMITH

Permit Application Clearance Information

ZI Cleared 9/16/2020 LAUREN PADICK
Roof/Waste drainage to street Cleared 9/18/2020 ADRIAN CASTRO
Sewer availability Cleared 9/18/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/21/2020 ADRIAN CASTRO

Contact Information

Contractor Better Together Builders Inc; Lic. No.: 1047689-B 16430 VENTURA BLVD #304      ENCINO, CA 91436
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/18/2020 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 11/30/2020 Partial Approval STEVEN BACK
Footing/Foundation/Slab 11/30/2020 No Access for Inspection STEVEN BACK
PLUMBING-Rough 12/15/2020 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 12/21/2020 Partial Approval STEVEN BACK
Footing/Foundation/Slab 12/21/2020 Partial Approval STEVEN BACK
Insulation 12/28/2020 Not Ready for Inspection DONALD SUNSERI
BUILDING-Rough-Frame 12/30/2020 Partial Approval VINCENT HANLEY
Insulation 12/30/2020 Partial Approval VINCENT HANLEY
PLUMBING-Rough 12/30/2020 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/5/2021 Not Ready for Inspection JOSEPH SAGEN
BUILDING-Rough-Frame 2/11/2021 Corrections Issued STEVEN BACK
ELECTRICAL-Final 2/11/2021 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 2/11/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 2/11/2021 Corrections Issued STEVEN BACK
Green Building Rough 2/11/2021 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 2/22/2021 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 2/22/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 2/22/2021 Approved STEVEN BACK
PLUMBING-Rough 2/22/2021 Corrections Issued STEVEN BACK
Green Building Rough 2/26/2021 Approved STEVEN BACK
Interior/Exterior Lathing 2/26/2021 Partial Approval STEVEN BACK
PLUMBING-Rough 2/26/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 3/2/2021 Approved STEVEN BACK
Insulation 3/2/2021 Approved STEVEN BACK
Drywall Nailing 3/9/2021 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 3/9/2021 Partial Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 4/22/2021 Corrections Issued STEVEN BACK
Final 4/22/2021 Not Ready for Inspection STEVEN BACK
Footing/Foundation/Slab 4/22/2021 Approved STEVEN BACK
Green Building Final 4/22/2021 Not Ready for Inspection STEVEN BACK
HVAC-Final 4/22/2021 Corrections Issued STEVEN BACK
PLUMBING-Final 4/22/2021 Corrections Issued STEVEN BACK
SGSOV-Seismic Gas S/O Valve 4/22/2021 SGSOV Approved STEVEN BACK
Smoke Detectors 4/22/2021 Corrections Issued STEVEN BACK
ELECTRICAL-Final 5/17/2021 Corrections Issued VINCENT HANLEY
Final 5/17/2021 Corrections Issued VINCENT HANLEY
Green Building Final 5/17/2021 Approved VINCENT HANLEY
Smoke Detectors 5/17/2021 Corrections Issued VINCENT HANLEY
Final 6/16/2021 Corrections Issued VINCENT HANLEY
Smoke Detectors 6/16/2021 Approved VINCENT HANLEY
Final 7/6/2021 Conditional Approval MICHAEL PELHAM