10306 N FERNGLEN AVE 91042
Certificate Information: 10306 N FERNGLEN AVE 91042
- Application / Permit
- 20014-20000-03473
- Plan Check / Job No.
- B20VN10609
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 11'6" X 7'5" MASTER BATHROOM ADDITION TO THE (E) SFD.
- Permit Issued
- Issued on 8/12/2021
- Issuing Office
- Current Status
- CofO Issued on 11/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2020 | RAHEL BEYENE |
| Corrections Issued | 9/2/2020 | RAHEL BEYENE |
| Applicant returned to address corrections | 11/20/2020 | PINANK PATEL |
| Applicant returned to address corrections | 1/29/2021 | PINANK PATEL |
| Applicant returned to address corrections | 7/9/2021 | PINANK PATEL |
| Plan Check Approved | 8/12/2021 | PINANK PATEL |
| Issued | 8/12/2021 | APPLICANT |
| Building Plans Picked Up | 8/17/2021 | APPLICANT |
| CofO in Progress | 11/12/2021 | MATTHEW NELSON |
| Permit Finaled | 11/22/2021 | MICHAEL SMITH |
| CofO Issued | 11/22/2021 | MICHAEL SMITH |
| Permit Finaled | 11/22/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/15/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 10/15/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2020 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 7/12/2021 | PINANK PATEL |
| Specific Plan | Cleared | 7/26/2021 | MIGUEL GAMBOA |
Contact Information
| Contractor | Pro Star Builders Inc; Lic. No.: 1053661-B | 17412 VENTURA BLVD SUITE 151 ENCINO, CA 91316 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/31/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/9/2021 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/23/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 9/23/2021 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 9/23/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 9/23/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 9/23/2021 | Approved | MATTHEW NELSON |
| Insulation | 9/30/2021 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 9/30/2021 | Approved | AMY COLIN |
| Shower Pan | 9/30/2021 | Not Ready for Inspection | AMY COLIN |
| Drywall Nailing | 10/4/2021 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 10/4/2021 | Approved | WILLIAM WREN |
| Shower Pan | 10/4/2021 | Approved | WILLIAM WREN |
| ELECTRICAL-Final | 11/8/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 11/8/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 11/8/2021 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Final | 11/8/2021 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Final | 11/8/2021 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/8/2021 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 11/8/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 11/10/2021 | Approved | MATTHEW NELSON |
| Final | 11/10/2021 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 11/10/2021 | Approved | MATTHEW NELSON |
| HVAC-Final | 11/10/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 11/10/2021 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/10/2021 | SGSOV Approved | MATTHEW NELSON |