7029 N CALHOUN AVE 91405
Certificate Information: 7029 N CALHOUN AVE 91405
- Application / Permit
- 20014-20000-03460
- Plan Check / Job No.
- B20VN10566
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SINGLE STORY ADDITION OF IRREGULAR 17.83' x 32.42' TO THE (E) SINGLE-FAMILY DWELLING.
- Permit Issued
- Issued on 12/15/2020
- Issuing Office
- Current Status
- CofO Issued on 9/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2020 | LUIS RINCON |
| Corrections Issued | 8/20/2020 | LUIS RINCON |
| Applicant returned to address corrections | 8/31/2020 | LUIS RINCON |
| Applicant returned to address corrections | 10/26/2020 | LUIS RINCON |
| Plan Check Approved | 11/15/2020 | LUIS RINCON |
| Issued | 12/15/2020 | APPLICANT |
| CofO in Progress | 8/3/2021 | JENNIFER RABUCHIN |
| CofO Issued | 9/25/2021 | MICHAEL SMITH |
| Permit Finaled | 9/25/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/3/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/23/2020 | Conditional Approval | DANIEL DREW |
| Pre-Inspection | 12/23/2020 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 1/7/2021 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 1/7/2021 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 1/7/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 1/21/2021 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 1/21/2021 | Partial Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/21/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/27/2021 | Corrections Issued | DAVID SCANTLIN |
| Green Building Rough | 1/27/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 1/27/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Wood Frame | 1/27/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 1/28/2021 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/28/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 2/22/2021 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 3/2/2021 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 3/5/2021 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/24/2021 | Partial Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/24/2021 | Partial Inspection | MICHEL ABAJAN |
| Green Building Rough | 3/24/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/18/2021 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/18/2021 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 5/18/2021 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/24/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/24/2021 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2021 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 5/24/2021 | Approved | MICHEL ABAJAN |
| Insulation | 6/3/2021 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/3/2021 | Approved | MORRIS JACKSON |
| Drywall Nailing | 6/9/2021 | Approved | MORRIS JACKSON |
| Final | 8/2/2021 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Final | 8/2/2021 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/2/2021 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 8/2/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 8/4/2021 | Approved | JENNIFER RABUCHIN |
| Final | 8/4/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 8/4/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/4/2021 | Approved | JENNIFER RABUCHIN |