8736 N ETIWANDA AVE 91325

Certificate Information: 8736 N ETIWANDA AVE 91325

Application / Permit
20014-20000-03459
Plan Check / Job No.
B20VN10564
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD IRREGULAR 16'-11" X 36'-2" FOR NEW LIVING ROOM/FULL BATH AND WET BAR TO AN EXISTING GARAGE/ 2ND DWELLING UNIT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/2/2022
Issuing Office
Current Status
CofO Issued on 5/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2020 APPLICANT
Assigned to Plan Check Engineer 8/19/2020 SHANGQIN XIE
Corrections Issued 8/19/2020 SHANGQIN XIE
Applicant returned to address corrections 1/11/2021 JENNIFER LEE
Applicant returned to address corrections 3/16/2021 JENNIFER LEE
Plan Check Approved 4/19/2022 LUISANGEL VALENZUELA
Building Plans Picked Up 4/19/2022 APPLICANT
Issued 5/2/2022 APPLICANT
CofO in Progress 5/15/2023 JOHN KIDWELL
Permit Finaled 5/18/2023 JOHN JANSON
CofO Issued 5/18/2023 JOHN JANSON
Permit Finaled 5/18/2023 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/3/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 12/4/2020 ABDULLAH SADOZAI
Sewer availability Cleared 12/4/2020 GUILLERMO PETRA
Low Impact Development Cleared 4/7/2022 SUNG JOON WON

Contact Information

Architect Bhogal,, Jaswant Singh; Lic. No.: C13660 16650 LASSEN ST      NORTH HILLS, CA 91343
Contractor Owner-Builder       ,
Engineer Tagudar,, Fred; Lic. No.: C33612 255 W 5TH ST APT 706      SAN PEDRO, CA 90731

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/23/2022 Partial Approval JEFFREY PARD
Sewer 6/23/2022 Approved JEFFREY PARD
Footing/Foundation/Slab 7/8/2022 Approved JEFFREY PARD
ELECTRICAL-Rough 10/4/2022 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 10/4/2022 Approved DAVID SCANTLIN
HVAC-Rough 10/4/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 10/27/2022 Partial Approval JOHN KIDWELL
Green Building Rough 10/27/2022 Approved JOHN KIDWELL
Insulation 10/27/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 10/27/2022 Partial Approval JOHN KIDWELL
PLUMBING-Rough 10/27/2022 Approved JOHN KIDWELL
Pre-Inspection 10/27/2022 Partial Inspection JUSTIN HAWLEY
Pre-Inspection 10/27/2022 Partial Inspection MORRIS JACKSON
Special/Order Compliance 10/27/2022 Partial Inspection JESUS PINEDA
Special/Order Compliance 10/27/2022 Partial Inspection KRISTEN CAUSEY
Drywall Nailing 11/18/2022 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 4/17/2023 Approved DAVID SCANTLIN
Final 4/17/2023 Corrections Issued DAVID SCANTLIN
Green Building Final 4/17/2023 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 4/17/2023 SGSOV Not Ready DAVID SCANTLIN
Smoke Detectors 4/17/2023 Approved DAVID SCANTLIN
Special/Order Compliance 4/17/2023 Partial Inspection MORRIS JACKSON
Final 5/15/2023 OK to Issue CofO JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 5/15/2023 SGSOV Approved JOHN KIDWELL