11114 N LEOLANG AVE 91040
Certificate Information: 11114 N LEOLANG AVE 91040
- Application / Permit
- 20014-20000-03437
- Plan Check / Job No.
- B20VN10493
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 12'-5" x 29'-0", 330 SQ. FT. ADDITION TO EXTEND LIVING ROOM AND (E) BEDROOM, ALSO ADD 30 SQ. FT. FOR NEW COVERED ENTRYWAY TO THE FRONT OF THE (E) DWELLING.
- Permit Issued
- Issued on 1/7/2021
- Issuing Office
- Current Status
- CofO Corrected on 11/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2020 | STANLEY RAAP |
| Corrections Issued | 8/19/2020 | STANLEY RAAP |
| Applicant returned to address corrections | 12/16/2020 | SARKIS HARABEDIAN |
| Plan Check Approved | 1/7/2021 | SARKIS HARABEDIAN |
| Issued | 1/7/2021 | APPLICANT |
| CofO in Progress | 8/3/2021 | MATTHEW NELSON |
| CofO Issued-Status Void | 11/13/2021 | MICHAEL SMITH |
| Permit Finaled-Status Void | 11/13/2021 | MICHAEL SMITH |
| Re-Activate Permit | 11/17/2021 | MICHAEL SMITH |
| CofO Corrected | 11/17/2021 | MICHAEL SMITH |
| Permit Finaled | 11/17/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 9/10/2020 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 10/15/2020 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/11/2021 | Corrections Issued | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 1/12/2021 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 3/2/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/12/2021 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 4/12/2021 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 4/12/2021 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/29/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 4/29/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/14/2021 | Approved | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 5/14/2021 | Approved | MATTHEW NELSON |
| Insulation | 5/20/2021 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 5/20/2021 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 5/28/2021 | Approved | MORRIS JACKSON |
| Final | 7/23/2021 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 7/23/2021 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 7/23/2021 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 7/23/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 8/3/2021 | Approved | MATTHEW NELSON |
| Final | 8/3/2021 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 8/3/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 8/3/2021 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 8/3/2021 | SGSOV Approved | MATTHEW NELSON |