24205 W VICTORY BLVD 91307

Certificate Information: 24205 W VICTORY BLVD 91307

Application / Permit
20014-20000-03431
Plan Check / Job No.
B20VN10474
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 9' X 20'4" AND 11'5" X 17'2" ADDITIONS TO AND CONVERT THE (E) 18' X 18' DETACHED CARPORT INTO A (N) ACCESSORY DWELLING UNIT AS PER GCS 65852.(E)(1)(B) , ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/31/2022
Issuing Office
Current Status
CofO Issued on 4/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/18/2020 APPLICANT
Assigned to Plan Check Engineer 8/21/2020 RARES BODEA
Corrections Issued 8/23/2020 RARES BODEA
Building Plans Picked Up 9/2/2020 APPLICANT
Applicant returned to address corrections 2/24/2021 RARES BODEA
Plan Check Approved 4/30/2021 RARES BODEA
Issued 5/31/2022 APPLICANT
CofO in Progress 4/20/2023 TROY SANDERS
Permit Finaled 4/25/2023 MICHAEL SMITH
CofO Issued 4/25/2023 MICHAEL SMITH
Permit Finaled 4/25/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/4/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 9/9/2020 GUILLERMO PETRA
Sewer availability Cleared 9/9/2020 GUILLERMO PETRA
Low Impact Development Cleared 2/11/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 2/23/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Shamsrad,, Shima; Lic. No.: C88470 6300 ORANGE STREET APT 3      LOS ANGELES, CA 90048

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/8/2022 Approved TROY SANDERS
Excavation/Setback/Form/Re-Bar 7/13/2022 Not Ready for Inspection TROY SANDERS
Footing/Foundation/Slab 7/13/2022 Partial Approval TROY SANDERS
Excavation/Setback/Form/Re-Bar 8/16/2022 Approved TROY SANDERS
PLUMBING-Rough 8/16/2022 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 9/13/2022 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/13/2022 Partial Approval TROY SANDERS
Green Building Rough 9/13/2022 Not Ready for Inspection TROY SANDERS
ELECTRICAL-Rough 9/15/2022 Approved TROY SANDERS
PLUMBING-Rough 9/15/2022 Approved TROY SANDERS
Green Building Rough 9/28/2022 Approved JESUS PINEDA
Insulation 9/28/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 9/28/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 10/20/2022 Approved MORRIS JACKSON
Shower Pan 10/20/2022 Approved MORRIS JACKSON
Drywall Nailing 10/26/2022 Approved MORRIS JACKSON
Final 4/19/2023 OK to Issue CofO TROY SANDERS
Footing/Foundation/Slab 4/19/2023 Approved TROY SANDERS
Green Building Final 4/19/2023 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 4/19/2023 SGSOV Approved TROY SANDERS
Smoke Detectors 4/19/2023 Approved TROY SANDERS
Special/Order Compliance 4/19/2023 Partial Inspection MORRIS JACKSON