4428 N PLACIDIA AVE 91602
Certificate Information: 4428 N PLACIDIA AVE 91602
- Application / Permit
- 20014-20000-03429
- Plan Check / Job No.
- B20VN10462
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) IRREGULAR SHAPED ADDITION 11'-6" X 31'-9" ADDITION TO FRONT, (N) 15'X 24'-7" IRREGULAR SHAPED ADDITION TO REAR AND REMODEL TO (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 1/19/2021
- Issuing Office
- Current Status
- CofO Issued on 10/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 9/10/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 9/17/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 9/18/2020 | APPLICANT |
| Plan Check Approved | 1/7/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 1/19/2021 | APPLICANT |
| CofO in Progress | 10/18/2021 | MICHAEL PELHAM |
| Permit Finaled | 10/27/2021 | MICHAEL SMITH |
| CofO Issued | 10/27/2021 | MICHAEL SMITH |
| Permit Finaled | 10/27/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| ZI | Cleared | 10/6/2020 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 10/7/2020 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 11/25/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 12/7/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Inzunza Builders Inc; Lic. No.: 1054458-B | 8413 CONKLIN ST DOWNEY, CA 90242 |
| Engineer | Terrio,, Greyson Franklin; Lic. No.: C87383 | 22647 VENTURA BLVD 362 WOODLAND HILLS, CA 91364 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/22/2021 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 1/29/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Piling/Pier/Caisson | 2/2/2021 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 2/5/2021 | Corrections Issued | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 2/6/2021 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2021 | Partial Approval | THOMAS FINNILA |
| Insulation | 2/22/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Sewer | 2/22/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2021 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 3/26/2021 | Partial Approval | THOMAS FINNILA |
| Wood Frame | 3/26/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2021 | Partial Approval | THOMAS FINNILA |
| Deputy Wood Construction | 4/12/2021 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2021 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 4/23/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2021 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 4/28/2021 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Rough | 4/28/2021 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 4/28/2021 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 5/6/2021 | Conditional Approval | THOMAS FINNILA |
| Green Building Rough | 5/6/2021 | Conditional Approval | THOMAS FINNILA |
| HVAC-Rough | 5/6/2021 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 5/12/2021 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 5/17/2021 | Approved | THOMAS FINNILA |
| Shower Pan | 5/21/2021 | Partial Approval | THOMAS FINNILA |
| Drywall Nailing | 5/24/2021 | Approved | THOMAS FINNILA |
| Green Building Rough | 5/24/2021 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 6/3/2021 | Approved | ALAN MORELOS |
| HVAC-Final | 8/23/2021 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 8/23/2021 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 9/9/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 9/9/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 9/9/2021 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 9/9/2021 | Approved | THOMAS FINNILA |
| HVAC-Final | 9/9/2021 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Final | 9/9/2021 | Approved | THOMAS FINNILA |
| Final | 10/1/2021 | Partial Approval | THOMAS FINNILA |
| Green Building Final | 10/1/2021 | Approved | THOMAS FINNILA |
| MERV13>=Final | 10/1/2021 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 10/1/2021 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 10/1/2021 | Approved | THOMAS FINNILA |
| Final | 10/15/2021 | OK to Issue CofO | THOMAS FINNILA |