13734 W MERCER ST 91331
Certificate Information: 13734 W MERCER ST 91331
- Application / Permit
- 20014-20000-03428
- Plan Check / Job No.
- B20VN10461
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 20' X 10' ADDITION TO AND CONVERT (E) 20' X 20' DETACHED GARAGE TO ACCESSORY DWELLING UNIT. WORK PER WFPP.
- Permit Issued
- Issued on 9/2/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/14/2020 | ROSENDO MEDINA |
| Corrections Issued | 8/15/2020 | ROSENDO MEDINA |
| Plan Check Approved | 9/2/2020 | ROSENDO MEDINA |
| Issued | 9/2/2020 | APPLICANT |
| CofO in Progress | 1/5/2021 | MICHEL ABAJAN |
| Permit Finaled | 1/23/2021 | MICHAEL SMITH |
| CofO Issued | 1/23/2021 | MICHAEL SMITH |
| Permit Finaled | 1/23/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/20/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 8/20/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 8/21/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/24/2020 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/5/2020 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 10/5/2020 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 10/5/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/15/2020 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 10/15/2020 | Approved | MICHEL ABAJAN |
| Green Building Rough | 10/15/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Rough | 10/15/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/15/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/21/2020 | Approved | MICHEL ABAJAN |
| Green Building Rough | 10/21/2020 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 10/21/2020 | Approved | MICHEL ABAJAN |
| Insulation | 10/23/2020 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 10/23/2020 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 10/27/2020 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/16/2020 | Approved | MICHEL ABAJAN |
| Final | 12/21/2020 | Corrections Issued | MICHAEL TEMPLE |
| Gas Test | 12/21/2020 | Approved | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 12/21/2020 | SGSOV Not Ready | MICHAEL TEMPLE |
| Smoke Detectors | 12/21/2020 | Approved | MICHAEL TEMPLE |
| ELECTRICAL-Final | 12/23/2020 | Approved | JENNIFER RABUCHIN |
| Final | 12/23/2020 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Final | 12/23/2020 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 12/23/2020 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 12/23/2020 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 12/23/2020 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 12/23/2020 | Approved | JENNIFER RABUCHIN |
| Final | 1/5/2021 | OK to Issue CofO | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/5/2021 | SGSOV Approved | MICHEL ABAJAN |