4937 N FULTON AVE 91423

Certificate Information: 4937 N FULTON AVE 91423

Application / Permit
20014-20000-03425
Plan Check / Job No.
B20VN10444
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE (E) 1369 SF WITH 18'-8" AT EASTERN PORTION OF (E) SFD TO REMAIN. REBUILD 40'-1" X 42'-4" IRREGULAR SHAPE 2-STORY SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 1/10/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2020 APPLICANT
Assigned to Plan Check Engineer 9/3/2020 RAPHAEL ROSAS
Corrections Issued 9/9/2020 RAPHAEL ROSAS
Quality Review Completed 9/9/2020 CHON CHIO KUO
Applicant returned to address corrections 6/4/2021 RAPHAEL ROSAS
Applicant returned to address corrections 7/27/2021 RAPHAEL ROSAS
Applicant returned to address corrections 11/3/2021 RAPHAEL ROSAS
Applicant returned to address corrections 12/15/2021 RAPHAEL ROSAS
Plan Check Approved 12/23/2021 RAPHAEL ROSAS
Building Plans Picked Up 1/4/2022 APPLICANT
Issued 1/10/2022 APPLICANT
CofO in Progress 10/15/2025 MISAEL ESPARZA
CofO Issued 11/20/2025 RUBEN SALAS
Permit Finaled 11/20/2025 RUBEN SALAS

Permit Application Clearance Information

ZI Cleared 12/2/2020 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 12/28/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 12/28/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 1/26/2021 MATTHEW CRAIG
Low Impact Development Cleared 5/15/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/24/2021 CARLOS AGUILERA

Contact Information

Contractor Landome Inc; Lic. No.: 1040389-B 7648 BECKETT ST      TUJUNGA, CA 91042
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/14/2022 Approved MISAEL ESPARZA
PLUMBING-Rough 4/19/2022 Partial Approval MISAEL ESPARZA
Deputy Drilled-In Anchors 4/26/2022 Conditional Approval MISAEL ESPARZA
Footing/Foundation/Slab 5/3/2022 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 6/22/2022 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 7/15/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 7/20/2022 Partial Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/16/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/19/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/23/2022 Partial Approval MICHEL ABAJAN
Deputy Wood Construction 3/16/2023 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 4/3/2023 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 4/3/2023 Corrections Issued JUAN VALENZUELA
Green Building Rough 4/3/2023 Corrections Issued JUAN VALENZUELA
HVAC-Rough 4/3/2023 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 4/3/2023 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 4/21/2023 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/21/2023 Partial Approval MISAEL ESPARZA
HVAC-Rough 4/21/2023 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 4/21/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 5/2/2023 Approved MISAEL ESPARZA
ELECTRICAL-Rough 5/2/2023 Approved MISAEL ESPARZA
Green Building Rough 5/2/2023 Approved MISAEL ESPARZA
HVAC-Rough 5/2/2023 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 5/2/2023 Approved MISAEL ESPARZA
Insulation 6/30/2023 Approved JOHN COLEMAN
Interior/Exterior Lathing 6/30/2023 Approved JOHN COLEMAN
Drywall Nailing 8/4/2023 Approved MISAEL ESPARZA
Shower Pan 9/14/2023 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 9/25/2023 Approved MISAEL ESPARZA
Final 6/12/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 6/12/2024 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 6/12/2024 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 6/12/2024 Approved MISAEL ESPARZA
Structural Steel Frame 6/12/2024 Partial Inspection MISAEL ESPARZA
Final 6/28/2024 Corrections Issued JACK KARGODORIAN
Green Building Final 6/28/2024 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 6/28/2024 SGSOV Not Ready JACK KARGODORIAN
Structural Steel Frame 6/28/2024 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Final 9/27/2024 Approved MISAEL ESPARZA
Final 9/27/2024 Corrections Issued MISAEL ESPARZA
Green Building Final 9/27/2024 Approved MISAEL ESPARZA
HVAC-Final 9/27/2024 Approved MISAEL ESPARZA
PLUMBING-Final 9/27/2024 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/27/2024 SGSOV Approved MISAEL ESPARZA
Structural Steel Frame 9/27/2024 Partial Inspection MISAEL ESPARZA
Final 10/29/2024 Conditional Approval MISAEL ESPARZA
Structural Steel Frame 10/29/2024 Approved MISAEL ESPARZA
Final 10/10/2025 OK to Issue CofO MISAEL ESPARZA