6945 N WOODLAKE AVE 91307

Certificate Information: 6945 N WOODLAKE AVE 91307

Application / Permit
20014-20000-03367
Plan Check / Job No.
B20VN10299
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 19'-5" X 20' TO EXISTING DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 10/28/2020
Issuing Office
Current Status
CofO Issued on 10/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/7/2020 APPLICANT
Assigned to Plan Check Engineer 8/14/2020 SELLA BENYAMIN
Corrections Issued 8/18/2020 SELLA BENYAMIN
Building Plans Picked Up 8/19/2020 APPLICANT
Plan Check Approved 10/15/2020 SELLA BENYAMIN
Issued 10/28/2020 APPLICANT
CofO in Progress 9/30/2021 TROY SANDERS
Permit Finaled 10/4/2021 JOHN JANSON
CofO Issued 10/4/2021 JOHN JANSON
Permit Finaled 10/4/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/25/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/25/2020 GABRIEL ROBLES
Sewer availability Cleared 8/25/2020 GABRIEL ROBLES
Hydrant and Access approval Cleared 9/23/2020 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 10/6/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/20/2020 Approved TROY SANDERS
Underground Mechanical 12/31/2020 Approved TROY SANDERS
Excavation/Setback/Form/Re-Bar 1/11/2021 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/4/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 2/19/2021 Approved TROY SANDERS
Green Building Rough 2/19/2021 Approved TROY SANDERS
Interior/Exterior Lathing 2/19/2021 Approved TROY SANDERS
Rough-Elec/Plmb/HVAC 2/19/2021 Approved TROY SANDERS
Drywall Nailing 2/26/2021 Approved TROY SANDERS
Underground Mechanical 3/11/2021 Approved TROY SANDERS
ELECTRICAL-Final 9/13/2021 Approved TROY SANDERS
Final 9/13/2021 Corrections Issued TROY SANDERS
Footing/Foundation/Slab 9/13/2021 Approved TROY SANDERS
Green Building Final 9/13/2021 Corrections Issued TROY SANDERS
HVAC-Final 9/13/2021 Approved TROY SANDERS
PLUMBING-Final 9/13/2021 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 9/13/2021 SGSOV Approved TROY SANDERS
Smoke Detectors 9/13/2021 Approved TROY SANDERS
Final 9/30/2021 OK to Issue CofO TROY SANDERS
Green Building Final 9/30/2021 Approved TROY SANDERS