ADD 22'-7" X 22'-2" IRREGULAR SHAPED ON FIRST FLOOR AND 22'-7" X 24'-5" ON SECOND FLOOR TO AND CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 2/26/2021
Issuing Office
Current Status
Issued on 2/26/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/14/2020 APPLICANT
Assigned to Plan Check Engineer 9/3/2020 SELLA BENYAMIN
Corrections Issued 9/11/2020 SELLA BENYAMIN
Quality Review Completed 9/17/2020 STEVEN KIM
Building Plans Picked Up 9/18/2020 APPLICANT
Plan Check Approved 2/26/2021 SELLA BENYAMIN
Issued 2/26/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/29/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 11/23/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 11/23/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 1/6/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 1/7/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 1/22/2021 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/29/2022 Partial Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 3/30/2022 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 3/30/2022 Partial Approval JACK KARGODORIAN
Deputy Drilled-In Anchors 4/21/2022 Conditional Approval CALEB MEISTER
Footing/Foundation/Slab 4/22/2022 Corrections Issued CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 4/26/2022 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 8/4/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 9/28/2023 Partial Approval JOHN HAYES
ELECTRICAL-Rough 9/28/2023 Not Ready for Inspection JOHN HAYES
Green Building Rough 9/28/2023 Not Ready for Inspection JOHN HAYES
HVAC-Rough 9/28/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 9/28/2023 Not Ready for Inspection JOHN HAYES
Special/Order Compliance 9/28/2023 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 10/23/2023 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 10/23/2023 Approved CHRISTOPHER ROJAS
Green Building Rough 10/23/2023 Approved CHRISTOPHER ROJAS
HVAC-Rough 10/23/2023 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 10/23/2023 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/31/2023 Approved KEVIN BERBERYAN
Footing/Foundation/Slab 10/31/2023 Corrections Issued KEVIN BERBERYAN
Interior/Exterior Lathing 10/31/2023 Approved KEVIN BERBERYAN
Insulation 11/7/2023 Approved JOHN HAYES
Shower Pan 11/7/2023 Approved JOHN HAYES
Drywall Nailing 11/30/2023 Approved JOHN HAYES
Interior/Exterior Lathing 11/30/2023 Approved JOHN HAYES
Underground Mechanical 2/23/2024 Partial Approval JOHN HAYES
Sewer 7/15/2025 Partial Approval ROBERTO PALACIOS-LOPEZ