11318-11320 W JOFFRE ST 90049
Certificate Information: 11318-11320 W JOFFRE ST 90049
- Application / Permit
- 20014-20000-03351
- Plan Check / Job No.
- B20VN10264
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 15'1" X 22'10" IRREGULAR SHAPED PORTION OF THE (E) GARAGE INTO A JUNIOR ACCESSORY DWELLING UNIT AS PER GCS 65852.2(E)(1) AND 65852.22 AND CONVERT (E) 5'3" X 18'3" IRREGULAR SHAPED PORTION OF GARAGE TO STORAGE ROOM, REPLACE DOOR AND WINDOW AT LIVING ROOM , REINFORCE ROOF BY SISTERING EXISTING ROOF FRAMING, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/19/2021
- Issuing Office
- Current Status
- CofO Issued on 11/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2020 | RARES BODEA |
| Corrections Issued | 9/20/2020 | RARES BODEA |
| Building Plans Picked Up | 9/22/2020 | APPLICANT |
| Plan Check Approved | 4/19/2021 | RARES BODEA |
| Issued | 4/19/2021 | APPLICANT |
| CofO in Progress | 10/25/2021 | CARLOS MATAMOROS |
| CofO in Progress | 11/1/2021 | CARLOS MATAMOROS |
| Permit Finaled | 11/22/2021 | DEROLD HAUFF |
| CofO Issued | 11/22/2021 | DEROLD HAUFF |
| Permit Finaled | 11/22/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 1/27/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/27/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/27/2021 | JOHN TRIANTAFYLLOS |
| Specific Plan | Cleared | 2/16/2021 | VALERIA CEJA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Other (see comments) | 5/11/2021 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 5/11/2021 | Conditional Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 5/25/2021 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 5/25/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Gas Test | 5/25/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 5/25/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| MERV13>=Rough | 5/25/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 5/25/2021 | Partial Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 6/4/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 6/4/2021 | Approved | CARLOS MATAMOROS |
| Gas Test | 6/4/2021 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 6/4/2021 | Approved | CARLOS MATAMOROS |
| MERV13>=Rough | 6/4/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 6/4/2021 | Approved | CARLOS MATAMOROS |
| Insulation | 6/11/2021 | Approved | AMY COLIN |
| Drywall Nailing | 6/30/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 8/31/2021 | Approved | CARLOS MATAMOROS |
| Final | 9/28/2021 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 9/28/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| MERV13>=Final | 9/28/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 9/28/2021 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 9/28/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 10/5/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 10/5/2021 | Corrections Issued | CARLOS MATAMOROS |
| Gas Test | 10/5/2021 | Approved | CARLOS MATAMOROS |
| Green Building Final | 10/5/2021 | Approved | CARLOS MATAMOROS |
| MERV13>=Final | 10/5/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 10/5/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Smoke Detectors | 10/5/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 10/15/2021 | Approved | CARLOS MATAMOROS |
| Final | 10/15/2021 | Partial Approval | CARLOS MATAMOROS |
| Gas Test | 10/15/2021 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 10/15/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 10/15/2021 | Approved | CARLOS MATAMOROS |
| Final | 10/21/2021 | OK to Issue CofO | CARLOS MATAMOROS |
| HVAC-Final | 10/21/2021 | Approved | CARLOS MATAMOROS |