10959-10961 N ELDORA AVE 91040
Certificate Information: 10959-10961 N ELDORA AVE 91040
- Application / Permit
- 20014-20000-03338
- Plan Check / Job No.
- B20VN10221
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ECPC: 83 SQ. FT. ADDITION TOO AND CONVERT THE (E) 446 SQ. FT. GARAGE INTO A (N) 549 SQ. FT. ACCESSORY DWELLING UNIT PER ENGINEERING PER 65852.2(e)(1)(A)
- Permit Issued
- Issued on 10/28/2020
- Issuing Office
- Current Status
- CofO Issued on 9/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2020 | RACHEL BEYENE |
| Corrections Issued | 8/10/2020 | RACHEL BEYENE |
| Plan Check Approved | 10/28/2020 | OMAR GARNICA |
| Issued | 10/28/2020 | APPLICANT |
| CofO in Progress | 9/13/2021 | MATTHEW NELSON |
| Permit Finaled | 9/15/2021 | MICHAEL SMITH |
| CofO Issued | 9/15/2021 | MICHAEL SMITH |
| Permit Finaled | 9/15/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| ZI | Cleared | 9/2/2020 | LAUREN PADICK |
| Address approval | Cleared | 9/4/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 9/4/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 9/9/2020 | GUILLERMO PETRA |
| Grading Pre-Inspection | Cleared | 9/15/2020 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mejia,, Fernando Finuliar; Lic. No.: C54382 | 8305 DUCOR AVE WEST HILLS, CA 91304 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/11/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 2/8/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 2/8/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/2/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 3/2/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 3/2/2021 | Approved | MATTHEW NELSON |
| Insulation | 3/12/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/12/2021 | Approved | MATTHEW NELSON |
| Drywall Nailing | 3/25/2021 | Approved | MATTHEW NELSON |
| Shower Pan | 3/25/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/9/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 8/3/2021 | Corrections Issued | MATTHEW NELSON |
| Final | 8/3/2021 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 8/3/2021 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 8/3/2021 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Final | 8/3/2021 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 8/3/2021 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 8/3/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 9/13/2021 | Approved | MATTHEW NELSON |
| Final | 9/13/2021 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 9/13/2021 | Approved | MATTHEW NELSON |
| HVAC-Final | 9/13/2021 | Approved | MATTHEW NELSON |