5646-5646 1/2 N CARTWRIGHT AVE 91601

Certificate Information: 5646-5646 1/2 N CARTWRIGHT AVE 91601

Application / Permit
20014-20000-03316
Plan Check / Job No.
B20VN10161
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
DEMO ENTIRE GARAGE EXCEPT 18LF OF NORTH & SOUTH WALLS & ADD 2-STORY SFD W/ ATTACHED 2-STORY ACCESSORY DWELLING UNIT & 1-CAR CARPORT (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 1/29/2021
Issuing Office
Current Status
CofO Issued on 2/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2020 APPLICANT
Assigned to Plan Check Engineer 8/27/2020 NILOOFAR MEHRAIN
Corrections Issued 9/3/2020 NILOOFAR MEHRAIN
Quality Review Completed 9/3/2020 CHON CHIO KUO
Building Plans Picked Up 9/4/2020 APPLICANT
Applicant returned to address corrections 10/1/2020 NILOOFAR MEHRAIN
Plan Check Approved 1/12/2021 NILOOFAR MEHRAIN
Issued 1/29/2021 APPLICANT
CofO in Progress 11/21/2021 DANIEL DREW
CofO Issued 2/1/2022 MICHAEL SMITH
Permit Finaled 2/1/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/10/2020 GUILLERMO PETRA
Permit Cleared 9/10/2020 GUILLERMO PETRA
Hydrant and Access approval Cleared 9/29/2020 MATTHEW CRAIG
Trees in Parkway Cleared 10/6/2020 JOHN KIM
Eng Process Fee Ord 176,300 Cleared 10/20/2020 GUILLERMO PETRA
Sewer availability Cleared 11/6/2020 GUILLERMO PETRA
Low Impact Development Cleared 11/18/2020 ANDRES COVARRUBIAS
Redevelopment Project Area Cleared 12/10/2020 GISELLE CORELLA
ZI Cleared 12/10/2020 GISELLE CORELLA
Green Code Cleared 1/12/2021 NILOOFAR MEHRAIN
Roof/Waste drainage to street Cleared 1/28/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/22/2021 Approved DANIEL DREW
Underground Mechanical 2/22/2021 Not Ready for Inspection DANIEL DREW
Footing/Foundation/Slab 3/2/2021 Approved DANIEL DREW
PLUMBING-Rough 3/2/2021 Partial Approval DANIEL DREW
Underground Mechanical 3/2/2021 Not Ready for Inspection DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 3/10/2021 Corrections Issued DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 3/16/2021 Partial Approval DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 4/26/2021 Not Ready for Inspection THOMAS FINNILA
Wood Frame 4/26/2021 Not Ready for Inspection THOMAS FINNILA
Deputy Wood Construction 4/27/2021 Conditional Approval DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 5/7/2021 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 5/20/2021 Corrections Issued ARAM AVEDISIAN
Green Building Rough 5/20/2021 Approved ARAM AVEDISIAN
HVAC-Rough 5/20/2021 Approved ARAM AVEDISIAN
PLUMBING-Rough 5/20/2021 Approved ARAM AVEDISIAN
Wood Frame 5/20/2021 Not Ready for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 6/2/2021 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 6/2/2021 Approved ARAM AVEDISIAN
Green Building Rough 6/2/2021 Approved ARAM AVEDISIAN
HVAC-Rough 6/2/2021 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 6/2/2021 Approved ARAM AVEDISIAN
HVAC-Rough 6/3/2021 Approved JENNIFER RABUCHIN
Insulation 6/3/2021 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 6/3/2021 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 6/11/2021 Approved ALAN MORELOS
Shower Pan 6/28/2021 Approved DANIEL DREW
Interior/Exterior Lathing 7/1/2021 Not Ready for Inspection JAVIER RAMOS JR
Service/Power Release 7/1/2021 Not Ready for Inspection DANIEL DREW
Interior/Exterior Lathing 7/9/2021 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 7/23/2021 Approved DANIEL DREW
PLUMBING-Rough 7/23/2021 Approved DANIEL DREW
Service/Power Release 7/26/2021 No Access for Inspection ARAM AVEDISIAN
Service/Power Release 7/29/2021 Not Ready for Inspection DANIEL DREW
Service/Power Release 8/4/2021 Not Ready for Inspection DANIEL DREW
Green Building Final 9/16/2021 No Access for Inspection DANIEL DREW
SGSOV-Seismic Gas S/O Valve 9/16/2021 SGSOV Not Ready DANIEL DREW
Smoke Detectors 9/16/2021 No Access for Inspection DANIEL DREW
Final 9/21/2021 Not Ready for Inspection DANIEL DREW
ELECTRICAL-Final 9/23/2021 Corrections Issued DANIEL DREW
PLUMBING-Final 9/23/2021 Corrections Issued DANIEL DREW
ELECTRICAL-Final 10/14/2021 Not Ready for Inspection DANIEL DREW
Final 10/14/2021 Not Ready for Inspection DANIEL DREW
Green Building Final 10/14/2021 Approved DANIEL DREW
HVAC-Final 10/14/2021 Approved DANIEL DREW
PLUMBING-Final 10/14/2021 Corrections Issued DANIEL DREW
SGSOV-Seismic Gas S/O Valve 10/14/2021 SGSOV Approved DANIEL DREW
Smoke Detectors 10/14/2021 Approved DANIEL DREW
ELECTRICAL-Final 11/3/2021 Approved DANIEL DREW
Final 11/3/2021 Corrections Issued DANIEL DREW
HVAC-Final 11/3/2021 Approved DANIEL DREW
PLUMBING-Final 11/3/2021 Approved DANIEL DREW
Final 11/19/2021 OK to Issue CofO DANIEL DREW