5945 N MANTON AVE 91367

Certificate Information: 5945 N MANTON AVE 91367

Application / Permit
20014-20000-03308
Plan Check / Job No.
B20VN10131
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ADDITION TO EXISITIN SFD AND GARAGE **SEE COMMENTS**
Permit Issued
Issued on 9/28/2020
Issuing Office
Current Status
CofO Issued on 5/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/18/2020 APPLICANT
Assigned to Plan Check Engineer 8/21/2020 FERNANDO FLORES
Corrections Issued 8/24/2020 FERNANDO FLORES
Plan Check Approved 9/28/2020 TROY DEGUZMAN
Issued 9/28/2020 APPLICANT
CofO in Progress 5/12/2021 TROY SANDERS
Permit Finaled 5/13/2021 JOHN JANSON
CofO Issued 5/13/2021 JOHN JANSON
Permit Finaled 5/13/2021 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/31/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 8/31/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 8/31/2020 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 9/15/2020 BRIAN MILLER

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/21/2021 Approved TROY SANDERS
Deputy Drilled-In Anchors 1/27/2021 Partial Approval TROY SANDERS
Footing/Foundation/Slab 1/28/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 2/23/2021 Approved TROY SANDERS
ELECTRICAL-Rough 2/23/2021 Approved TROY SANDERS
Green Building Rough 2/23/2021 Not Ready for Inspection TROY SANDERS
PLUMBING-Rough 2/23/2021 Approved TROY SANDERS
Green Building Rough 3/1/2021 Approved TROY SANDERS
Insulation 3/1/2021 Approved TROY SANDERS
Interior/Exterior Lathing 3/1/2021 Approved TROY SANDERS
Drywall Nailing 3/4/2021 Approved TROY SANDERS
Shower Pan 3/4/2021 Approved TROY SANDERS
Interior/Exterior Lathing 3/8/2021 Approved TROY SANDERS
ELECTRICAL-Final 4/16/2021 Approved TROY SANDERS
Final 4/16/2021 Corrections Issued TROY SANDERS
Green Building Final 4/16/2021 Corrections Issued TROY SANDERS
HVAC-Final 4/16/2021 Approved TROY SANDERS
PLUMBING-Final 4/16/2021 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 4/16/2021 SGSOV Approved TROY SANDERS
Service/Power Release 4/16/2021 Approved TROY SANDERS
Smoke Detectors 4/16/2021 Corrections Issued TROY SANDERS
Final 5/12/2021 OK to Issue CofO TROY SANDERS
Green Building Final 5/12/2021 Approved TROY SANDERS
Smoke Detectors 5/12/2021 Approved TROY SANDERS