16389 W MIDWOOD DR 91344
Certificate Information: 16389 W MIDWOOD DR 91344
- Application / Permit
- 20014-20000-03288
- Plan Check / Job No.
- B20VN10052
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 8'-11" X 23'-8" ADDITION TO (E) SFD TO ENLARGE BEDROOM, W.I.C., & BATHROOM AND (N) POOL BATHROOM W/ EXTERIOR ACCESS ONLY. ALL WORK PER WFPP.
- Permit Issued
- Issued on 10/9/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2020 | RAPHAEL ROSAS |
| Corrections Issued | 8/13/2020 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 9/1/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 9/21/2020 | RAPHAEL ROSAS |
| Issued | 10/9/2020 | APPLICANT |
| CofO in Progress | 11/16/2021 | MARK JOHNSON |
| Permit Finaled | 8/30/2022 | DANIEL ORRANTE |
| CofO Issued | 8/30/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/30/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/18/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 8/18/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2020 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 9/8/2020 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/1/2021 | No Access for Inspection | MARK JOHNSON |
| Excavation/Setback/Form/Re-Bar | 4/5/2021 | Not Ready for Inspection | MARK JOHNSON |
| Pre-Inspection | 4/5/2021 | Partial Inspection | MARK JOHNSON |
| Underground Mechanical | 4/5/2021 | Corrections Issued | MARK JOHNSON |
| Excavation/Setback/Form/Re-Bar | 4/9/2021 | Approved | MARK JOHNSON |
| Underground Mechanical | 4/9/2021 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 5/4/2021 | Not Ready for Inspection | MARK JOHNSON |
| ELECTRICAL-Rough | 5/4/2021 | Not Ready for Inspection | MARK JOHNSON |
| Green Building Rough | 5/4/2021 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 5/4/2021 | Not Ready for Inspection | MARK JOHNSON |
| Rough-Elec/Plmb/HVAC | 5/4/2021 | Not Ready for Inspection | MARK JOHNSON |
| ELECTRICAL-Rough | 5/10/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 5/10/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 5/14/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 5/14/2021 | Approved | MARK JOHNSON |
| HVAC-Rough | 5/14/2021 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 5/14/2021 | Approved | MARK JOHNSON |
| Insulation | 5/20/2021 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 5/27/2021 | Approved | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 6/4/2021 | Corrections Issued | DEANDRE HOFFMAN |
| Shower Pan | 6/4/2021 | Corrections Issued | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 6/10/2021 | Approved | LILIANA PORTILLO |
| Shower Pan | 6/10/2021 | Approved | LILIANA PORTILLO |
| Final | 7/13/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 7/13/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Green Building Final | 7/13/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 7/13/2021 | SGSOV Not Ready | MICHAEL TEMPLE |
| Smoke Detectors | 7/13/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Final | 7/21/2021 | Corrections Issued | MARK JOHNSON |
| Footing/Foundation/Slab | 7/21/2021 | Approved | MARK JOHNSON |
| Green Building Final | 7/21/2021 | Approved | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 7/21/2021 | SGSOV Approved | MARK JOHNSON |
| Smoke Detectors | 7/21/2021 | Approved | MARK JOHNSON |
| Final | 11/15/2021 | OK to Issue CofO | MARK JOHNSON |