11555 W ADDISON ST 91601

Certificate Information: 11555 W ADDISON ST 91601

Application / Permit
20014-20000-03283
Plan Check / Job No.
B20VN10044
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
33'-8" ADDITION AND REMODEL TO RECONFIGURE (E) SINGLE FAMILY DWELLING PER ENGINEER.
Permit Issued
Issued on 3/8/2021
Issuing Office
Current Status
CofO Issued on 2/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/3/2020 APPLICANT
Assigned to Plan Check Engineer 8/7/2020 RAHEL BEYENE
Corrections Issued 8/10/2020 RAHEL BEYENE
Plan Check Approved 2/11/2021 JEROME MAGAT PALMA
Issued 3/8/2021 APPLICANT
Building Plans Picked Up 3/9/2021 APPLICANT
CofO in Progress 2/8/2022 CHRISTOPHE COCHRAN
CofO in Progress 2/8/2022 CHRISTOPHE COCHRAN
CofO Issued 2/12/2022 MICHAEL SMITH
Permit Finaled 2/12/2022 MICHAEL SMITH

Permit Application Clearance Information

Sewer availability Cleared 8/19/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 8/27/2020 JOHN TRIANTAFYLLOS
Specific Plan Cleared 10/8/2020 OLGA AYALA
Low Impact Development Cleared 1/14/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 1/21/2021 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/5/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 5/5/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 5/11/2021 Not Ready for Inspection THOMAS FINNILA
Pre-Inspection 5/11/2021 Not Ready for Inspection THOMAS FINNILA
Deputy Drilled-In Anchors 5/18/2021 Conditional Approval DANIEL ORRANTE
Footing/Foundation/Slab 5/20/2021 Conditional Approval THOMAS FINNILA
Deputy Reinf. Concrete 6/9/2021 No Access for Inspection ALAN MORELOS
Deputy Reinf. Concrete 6/10/2021 Approved ALAN MORELOS
PLUMBING-Rough 6/22/2021 Partial Approval THOMAS FINNILA
Wood Frame 6/22/2021 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/2/2021 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/14/2021 Partial Approval THOMAS FINNILA
PLUMBING-Rough 7/14/2021 Approved THOMAS FINNILA
ELECTRICAL-Rough 8/10/2021 Approved ARAM AVEDISIAN
HVAC-Rough 8/10/2021 Approved ARAM AVEDISIAN
Wood Frame 8/10/2021 Approved ARAM AVEDISIAN
Insulation 8/24/2021 Approved THOMAS FINNILA
Drywall Nailing 8/31/2021 Approved LILIANA PORTILLO
Green Building Rough 8/31/2021 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 10/25/2021 Approved JACK KARGODORIAN
Final 10/25/2021 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 10/25/2021 Approved JACK KARGODORIAN
Green Building Final 10/25/2021 Approved JACK KARGODORIAN
MERV13>=Final 10/25/2021 Approved JACK KARGODORIAN
MERV13>=Rough 10/25/2021 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 10/25/2021 SGSOV Gas Company JACK KARGODORIAN
Smoke Detectors 10/25/2021 Approved JACK KARGODORIAN
Final 11/5/2021 Not Ready for Inspection THOMAS FINNILA
Final 1/14/2022 Not Ready for Inspection THOMAS FINNILA
Final 1/20/2022 Corrections Issued MISAEL ESPARZA
Final 1/26/2022 OK to Issue CofO CHRISTOPHE COCHRAN