4261 S BEETHOVEN ST 90066

Certificate Information: 4261 S BEETHOVEN ST 90066

Application / Permit
20014-20000-03258
Plan Check / Job No.
B20VN10016
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL & 33'-9" X 19'-2" ADDITION TO 1ST FLOOR & CREATE 32'-8" X 27'-9" IRREGULAR SHAPE 2ND-FLOOR ADDITION (N) 1' X 6' COVERED PORCH. FIRE SPRINKLER REQUIRED NFPA-13D.
Permit Issued
Issued on 1/11/2024
Issuing Office
Valley
Current Status
CofO Issued on 9/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 SERGIO MUNIZ
Corrections Issued 9/22/2020 SERGIO MUNIZ
Quality Review Completed 9/23/2020 OMID HEDAYAT
Applicant returned to address corrections 5/4/2021 SERGIO MUNIZ
Building Plans Picked Up 5/7/2021 APPLICANT
Applicant returned to address corrections 9/9/2022 SERGIO MUNIZ
Plan Check Approved 9/16/2022 SERGIO MUNIZ
Issued 1/11/2024 APPLICANT
CofO in Progress 9/10/2025 WILBER ROSALES
Permit Finaled 9/10/2025 RICHARD STEINBACH
CofO Issued 9/10/2025 RICHARD STEINBACH
Permit Finaled 9/10/2025 RICHARD STEINBACH

Permit Application Clearance Information

Sewer availability Cleared 3/11/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 3/12/2021 DINAH GARIN
Specific Plan Cleared 5/25/2021 PEDRO AYALA
Low Impact Development Cleared 6/17/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/30/2021 DINAH GARIN

Contact Information

Contractor Onmark Builders; Lic. No.: 1061309-B 5907 RHODES AVE      VALLEY VILLAGE, CA 91607
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/20/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/10/2024 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 4/10/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/15/2024 Partial Approval TEMISTOCLES CAAL
PLUMBING-Rough 4/15/2024 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 5/7/2024 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 5/9/2024 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/3/2024 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/23/2024 Corrections Issued JESUS PINEDA
HVAC-Rough 8/23/2024 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 8/27/2024 Not Ready for Inspection JESUS PINEDA
HVAC-Rough 8/27/2024 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 8/30/2024 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 8/30/2024 Corrections Issued JESUS PINEDA
Deputy Other (see comments) 9/23/2024 Conditional Approval JESUS PINEDA
ELECTRICAL-Rough 10/8/2024 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/8/2024 Conditional Approval JESUS PINEDA
Green Building Rough 10/8/2024 Corrections Issued JESUS PINEDA
HVAC-Rough 10/8/2024 Approved JESUS PINEDA
PLUMBING-Rough 10/8/2024 Approved JESUS PINEDA
Sewer 10/8/2024 Approved JESUS PINEDA
ELECTRICAL-Rough 10/30/2024 Approved JESUS PINEDA
Gas Test 10/30/2024 Partial Approval JESUS PINEDA
Special/Order Compliance 10/30/2024 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 11/22/2024 Approved JESUS PINEDA
Green Building Rough 11/22/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 11/22/2024 Partial Approval JESUS PINEDA
Special/Order Compliance 11/22/2024 Corrections Issued JESUS PINEDA
Verify Sprinkler Sign Off 11/22/2024 Approved JESUS PINEDA
Insulation 12/4/2024 Approved JESUS PINEDA
Shower Pan 12/4/2024 Approved JESUS PINEDA
Drywall Nailing 12/13/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 12/17/2024 Approved REGINA MENDEZ
Special/Order Compliance 12/17/2024 Partial Inspection JAYLIN GRAVITTE
ELECTRICAL-Final 7/16/2025 Corrections Issued EUGENE CASSIDY
PLUMBING-Final 7/16/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 7/22/2025 Approved WILBER ROSALES
HVAC-Final 8/8/2025 Approved MICHAEL ALLEN
Final 9/4/2025 Conditional Approval WILBER ROSALES
Green Building Final 9/4/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 9/4/2025 SGSOV Approved WILBER ROSALES
Smoke Detectors 9/4/2025 Approved WILBER ROSALES
Final 9/8/2025 OK to Issue CofO WILBER ROSALES