4261 S BEETHOVEN ST 90066
Certificate Information: 4261 S BEETHOVEN ST 90066
- Application / Permit
- 20014-20000-03258
- Plan Check / Job No.
- B20VN10016
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL & 33'-9" X 19'-2" ADDITION TO 1ST FLOOR & CREATE 32'-8" X 27'-9" IRREGULAR SHAPE 2ND-FLOOR ADDITION (N) 1' X 6' COVERED PORCH. FIRE SPRINKLER REQUIRED NFPA-13D.
- Permit Issued
- Issued on 1/11/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | SERGIO MUNIZ |
| Corrections Issued | 9/22/2020 | SERGIO MUNIZ |
| Quality Review Completed | 9/23/2020 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/4/2021 | SERGIO MUNIZ |
| Building Plans Picked Up | 5/7/2021 | APPLICANT |
| Applicant returned to address corrections | 9/9/2022 | SERGIO MUNIZ |
| Plan Check Approved | 9/16/2022 | SERGIO MUNIZ |
| Issued | 1/11/2024 | APPLICANT |
| CofO in Progress | 9/10/2025 | WILBER ROSALES |
| Permit Finaled | 9/10/2025 | RICHARD STEINBACH |
| CofO Issued | 9/10/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/10/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/11/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2021 | DINAH GARIN |
| Specific Plan | Cleared | 5/25/2021 | PEDRO AYALA |
| Low Impact Development | Cleared | 6/17/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 6/30/2021 | DINAH GARIN |
Contact Information
| Contractor | Onmark Builders; Lic. No.: 1061309-B | 5907 RHODES AVE VALLEY VILLAGE, CA 91607 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/20/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2024 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 4/10/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2024 | Partial Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 4/15/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2024 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 8/23/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 8/27/2024 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Rough | 8/27/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 8/30/2024 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | Corrections Issued | JESUS PINEDA |
| Deputy Other (see comments) | 9/23/2024 | Conditional Approval | JESUS PINEDA |
| ELECTRICAL-Rough | 10/8/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2024 | Conditional Approval | JESUS PINEDA |
| Green Building Rough | 10/8/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 10/8/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 10/8/2024 | Approved | JESUS PINEDA |
| Sewer | 10/8/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 10/30/2024 | Approved | JESUS PINEDA |
| Gas Test | 10/30/2024 | Partial Approval | JESUS PINEDA |
| Special/Order Compliance | 10/30/2024 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 11/22/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 11/22/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 11/22/2024 | Partial Approval | JESUS PINEDA |
| Special/Order Compliance | 11/22/2024 | Corrections Issued | JESUS PINEDA |
| Verify Sprinkler Sign Off | 11/22/2024 | Approved | JESUS PINEDA |
| Insulation | 12/4/2024 | Approved | JESUS PINEDA |
| Shower Pan | 12/4/2024 | Approved | JESUS PINEDA |
| Drywall Nailing | 12/13/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 12/17/2024 | Approved | REGINA MENDEZ |
| Special/Order Compliance | 12/17/2024 | Partial Inspection | JAYLIN GRAVITTE |
| ELECTRICAL-Final | 7/16/2025 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Final | 7/16/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 7/22/2025 | Approved | WILBER ROSALES |
| HVAC-Final | 8/8/2025 | Approved | MICHAEL ALLEN |
| Final | 9/4/2025 | Conditional Approval | WILBER ROSALES |
| Green Building Final | 9/4/2025 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 9/4/2025 | SGSOV Approved | WILBER ROSALES |
| Smoke Detectors | 9/4/2025 | Approved | WILBER ROSALES |
| Final | 9/8/2025 | OK to Issue CofO | WILBER ROSALES |