14245 W HATTERAS ST 91401

Certificate Information: 14245 W HATTERAS ST 91401

Application / Permit
20014-20000-03256
Plan Check / Job No.
B20VN10010
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL & ADDITION TO (E) SFD FIRE SPRINKLERS NFPA- 13D
Permit Issued
Issued on 4/18/2022
Issuing Office
Current Status
CofO Issued on 2/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 MOHAMMAD ESMAILI
Corrections Issued 8/26/2020 MOHAMMAD ESMAILI
Quality Review Completed 9/18/2020 OMID HEDAYAT
Building Plans Picked Up 9/23/2020 APPLICANT
Applicant returned to address corrections 1/27/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 4/14/2022 MOHAMMAD ESMAILI
Plan Check Approved 4/18/2022 MOHAMMAD ESMAILI
Issued 4/18/2022 APPLICANT
CofO in Progress 1/18/2023 RYAN SALAZAR
Permit Finaled 2/13/2023 MICHAEL SMITH
CofO Issued 2/13/2023 MICHAEL SMITH
Permit Finaled 2/13/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/14/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 10/14/2021 GABRIEL ROBLES
Sewer availability Cleared 10/14/2021 GABRIEL ROBLES
Low Impact Development Cleared 2/3/2022 TA ANH
Roof/Waste drainage to street Cleared 2/8/2022 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/21/2022 Approved RICHARD DOCKUS
Gas Test 7/11/2022 Approved ALAN MORELOS
Sewer 7/11/2022 Approved ALAN MORELOS
Underground Mechanical 7/11/2022 Approved ALAN MORELOS
BUILDING-Rough-Frame 7/15/2022 Partial Approval RICHARD DOCKUS
Insulation 7/15/2022 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 7/19/2022 Partial Approval RICHARD DOCKUS
Wood Frame 8/31/2022 Partial Approval RICHARD DOCKUS
HVAC-Rough 9/6/2022 Approved RICHARD DOCKUS
Wood Frame 9/6/2022 Partial Approval RICHARD DOCKUS
ELECTRICAL-Rough 9/13/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 9/13/2022 Approved RICHARD DOCKUS
Interior/Exterior Lathing 9/20/2022 Partial Approval ASHLEY THOMPSON
Shower Pan 9/20/2022 Approved ASHLEY THOMPSON
Insulation 9/23/2022 Approved ASHLEY THOMPSON
Drywall Nailing 9/30/2022 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 9/30/2022 Approved DEANDRE HOFFMAN
Gas Test 11/7/2022 Approved THOMAS FINNILA
BUILDING-Rough-Frame 12/19/2022 Approved RYAN SALAZAR
Final 12/19/2022 Corrections Issued RYAN SALAZAR
Green Building Final 12/19/2022 Approved RYAN SALAZAR
Green Building Rough 12/19/2022 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 12/19/2022 SGSOV Approved RYAN SALAZAR
Smoke Detectors 12/19/2022 Approved RYAN SALAZAR
ELECTRICAL-Final 1/18/2023 Approved RYAN SALAZAR
Final 1/18/2023 OK to Issue CofO RYAN SALAZAR
HVAC-Final 1/18/2023 Approved RYAN SALAZAR
PLUMBING-Final 1/18/2023 Approved RYAN SALAZAR
Service/Power Release 1/18/2023 Approved RYAN SALAZAR