14245 W HATTERAS ST 91401
Certificate Information: 14245 W HATTERAS ST 91401
- Application / Permit
- 20014-20000-03256
- Plan Check / Job No.
- B20VN10010
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL & ADDITION TO (E) SFD FIRE SPRINKLERS NFPA- 13D
- Permit Issued
- Issued on 4/18/2022
- Issuing Office
- Current Status
- CofO Issued on 2/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 8/26/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 9/18/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 9/23/2020 | APPLICANT |
| Applicant returned to address corrections | 1/27/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 4/14/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 4/18/2022 | MOHAMMAD ESMAILI |
| Issued | 4/18/2022 | APPLICANT |
| CofO in Progress | 1/18/2023 | RYAN SALAZAR |
| Permit Finaled | 2/13/2023 | MICHAEL SMITH |
| CofO Issued | 2/13/2023 | MICHAEL SMITH |
| Permit Finaled | 2/13/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/14/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 10/14/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 2/3/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 2/8/2022 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/21/2022 | Approved | RICHARD DOCKUS |
| Gas Test | 7/11/2022 | Approved | ALAN MORELOS |
| Sewer | 7/11/2022 | Approved | ALAN MORELOS |
| Underground Mechanical | 7/11/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 7/15/2022 | Partial Approval | RICHARD DOCKUS |
| Insulation | 7/15/2022 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2022 | Partial Approval | RICHARD DOCKUS |
| Wood Frame | 8/31/2022 | Partial Approval | RICHARD DOCKUS |
| HVAC-Rough | 9/6/2022 | Approved | RICHARD DOCKUS |
| Wood Frame | 9/6/2022 | Partial Approval | RICHARD DOCKUS |
| ELECTRICAL-Rough | 9/13/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 9/13/2022 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 9/20/2022 | Partial Approval | ASHLEY THOMPSON |
| Shower Pan | 9/20/2022 | Approved | ASHLEY THOMPSON |
| Insulation | 9/23/2022 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 9/30/2022 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 9/30/2022 | Approved | DEANDRE HOFFMAN |
| Gas Test | 11/7/2022 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 12/19/2022 | Approved | RYAN SALAZAR |
| Final | 12/19/2022 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 12/19/2022 | Approved | RYAN SALAZAR |
| Green Building Rough | 12/19/2022 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 12/19/2022 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 12/19/2022 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 1/18/2023 | Approved | RYAN SALAZAR |
| Final | 1/18/2023 | OK to Issue CofO | RYAN SALAZAR |
| HVAC-Final | 1/18/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 1/18/2023 | Approved | RYAN SALAZAR |
| Service/Power Release | 1/18/2023 | Approved | RYAN SALAZAR |