4909 N VARNA AVE 91423

Certificate Information: 4909 N VARNA AVE 91423

Application / Permit
20014-20000-03250
Plan Check / Job No.
B20VN09995
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ALL EXTERIOR AND INTERIOR WALLS OF AN EXISTING ONE STORY SINGLE FAMILY DWELLING EXCEPT FOR 49'1" LF AT NORTH SIDE AND BUILD AN IRREGULAR SHAPED 86'6" X 41'-5" ONE STORY SINGLE FAMILY DWELLING WITH AN ATTACHED 19'-6" X 18'7" TWO CAR GARAGE AND WITH (N) 17'-6" X 10'-5" REAR TRELLIS, ALL WORK PER ENGINEERING NFPA-13D FIRE SPRINKLERS THROUGHOUT REQUIRED
Permit Issued
Issued on 7/22/2021
Issuing Office
Current Status
CofO Issued on 7/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 8/25/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 9/18/2020 OMID HEDAYAT
Building Plans Picked Up 9/21/2020 APPLICANT
Applicant returned to address corrections 5/27/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 6/7/2021 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 6/21/2021 SEWADA ZADOORAN MILAGARDI
Issued 7/22/2021 APPLICANT
CofO in Progress 6/17/2022 MISAEL ESPARZA
CofO Issued 7/18/2022 MICHAEL SMITH
Permit Finaled 7/18/2022 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 12/3/2020 MITESH PATEL
Permit Cleared 12/23/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 12/23/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 12/31/2020 GUILLERMO PETRA
Sewer availability Cleared 12/31/2020 GUILLERMO PETRA
Hydrant and Access approval Cleared 2/10/2021 MATTHEW CRAIG
ZI Cleared 4/13/2021 LAUREN PADICK
Trees in Parkway Cleared 4/29/2021 JOHN KIM

Contact Information

Contractor Owner-Builder       ,
Engineer Sin,, John P; Lic. No.: C91162 122 N GRAMERCY PL      LOS ANGELES, CA 90004

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/6/2021 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 8/12/2021 Corrections Issued CHARLES POWELL
Footing/Foundation/Slab 8/12/2021 Conditional Approval CHARLES POWELL
BUILDING-Rough-Frame 9/7/2021 Partial Inspection DANIEL DREW
PLUMBING-Rough 9/7/2021 Partial Approval DANIEL DREW
Insulation 9/10/2021 Partial Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/15/2021 Corrections Issued MISAEL ESPARZA
Deputy Wood Construction 9/16/2021 Conditional Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/8/2021 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/13/2021 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/18/2021 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 10/27/2021 Approved MISAEL ESPARZA
PLUMBING-Rough 10/27/2021 Approved MISAEL ESPARZA
HVAC-Rough 11/3/2021 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 11/8/2021 Partial Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 11/22/2021 Corrections Issued MISAEL ESPARZA
Green Building Rough 11/22/2021 Not Ready for Inspection MISAEL ESPARZA
Deputy Wood Construction 11/24/2021 Conditional Approval MISAEL ESPARZA
Special/Order Compliance 11/29/2021 Approved MISAEL ESPARZA
Insulation 12/6/2021 Partial Approval ASHLEY THOMPSON
Interior/Exterior Lathing 12/6/2021 Partial Approval ASHLEY THOMPSON
Drywall Nailing 12/13/2021 Corrections Issued MISAEL ESPARZA
Green Building Rough 12/13/2021 Approved MISAEL ESPARZA
Interior/Exterior Lathing 12/30/2021 Partial Approval JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 3/21/2022 SGSOV Not Ready MISAEL ESPARZA
BUILDING-Rough-Frame 5/23/2022 No Access for Inspection MISAEL ESPARZA
Drywall Nailing 5/23/2022 Conditional Approval MISAEL ESPARZA
Final 5/23/2022 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 5/23/2022 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 5/23/2022 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 5/23/2022 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 5/23/2022 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 6/1/2022 Approved MISAEL ESPARZA
Drywall Nailing 6/1/2022 Approved MISAEL ESPARZA
Final 6/1/2022 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 6/1/2022 Approved MISAEL ESPARZA
Green Building Final 6/1/2022 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 6/1/2022 Approved MISAEL ESPARZA
Final 6/6/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 6/16/2022 Approved MISAEL ESPARZA
Final 6/16/2022 OK to Issue CofO MISAEL ESPARZA
Green Building Final 6/16/2022 Approved MISAEL ESPARZA
HVAC-Final 6/16/2022 Approved MISAEL ESPARZA
PLUMBING-Final 6/16/2022 Approved MISAEL ESPARZA
Service/Power Release 6/17/2022 Approved MISAEL ESPARZA