5363 N VELOZ AVE 91356
Certificate Information: 5363 N VELOZ AVE 91356
- Application / Permit
- 20014-20000-03236
- Plan Check / Job No.
- B20VN09976
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 11'-6" X 20'-3" AND 5'-10" X 20' IRREGULAR SHAPE TO GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 9/17/2020
- Issuing Office
- Current Status
- CofO Issued on 3/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2020 | SELLA BENYAMIN |
| Corrections Issued | 8/14/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 8/17/2020 | APPLICANT |
| Issued | 9/17/2020 | APPLICANT |
| CofO in Progress | 3/12/2021 | DAVID SANDOVAL |
| Permit Finaled | 3/12/2021 | RONALD MYRICK |
| CofO Issued | 3/12/2021 | RONALD MYRICK |
| Permit Finaled | 3/12/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 8/18/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 8/18/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 8/18/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 8/25/2020 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2020 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 9/3/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kazarians,, Ardashes; Lic. No.: C36687 | 1528 CANADA BLVD STE 206 GLENDALE, CA 91208 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/1/2020 | Approved | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 10/7/2020 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 10/9/2020 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 10/9/2020 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2020 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2020 | Partial Approval | DAVID SANDOVAL |
| PLUMBING-Rough | 12/4/2020 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 12/10/2020 | Approved | RONALD COWAN |
| HVAC-Rough | 12/10/2020 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 12/18/2020 | Corrections Issued | DAVID SANDOVAL |
| ELECTRICAL-Rough | 12/18/2020 | Approved | DAVID SANDOVAL |
| Green Building Rough | 12/18/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| Grounding or Bonding | 12/18/2020 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 12/24/2020 | Approved | DAVID SANDOVAL |
| Green Building Rough | 12/24/2020 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 12/24/2020 | Partial Approval | DAVID SANDOVAL |
| Insulation | 12/29/2020 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 1/5/2021 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 1/5/2021 | Approved | DAVID SANDOVAL |
| Shower Pan | 1/11/2021 | Approved | DAVID SANDOVAL |
| Final | 3/5/2021 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 3/5/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 3/5/2021 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 3/5/2021 | Approved | DAVID SANDOVAL |
| Final | 3/11/2021 | OK to Issue CofO | DAVID SANDOVAL |
| Green Building Final | 3/11/2021 | Approved | DAVID SANDOVAL |