11906 W MCDONALD ST 90230
Certificate Information: 11906 W MCDONALD ST 90230
- Application / Permit
- 20014-20000-03226
- Plan Check / Job No.
- B20VN09944
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 4' X 7' FRONT PORCH ADDITION TO THE (E) SFD, NEW 30'4" X 27'2" REAR ADDITON TO (E) SFD TO CREATE (2) BEDROOMS, MASTER W.I.C. , (2) BATHROOMS, POWDER ROOM , LAUNDRY AND INTERIOR REMODEL TO (E) SFD TO REMODEL , THE LIVING ROOM , KITCHEN, (2) BEDROOMS AND (1) BATHROOM , CONVERT DEN TO LIVING ROOM , WINDOWS CHANGEOUT , NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 10/30/2020
- Issuing Office
- Current Status
- Issued on 10/30/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2020 | RARES BODEA |
| Corrections Issued | 8/9/2020 | RARES BODEA |
| Building Plans Picked Up | 8/10/2020 | APPLICANT |
| Plan Check Approved | 10/30/2020 | RARES BODEA |
| Issued | 10/30/2020 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/25/2020 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2020 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 9/14/2020 | FREDDY GARCIA |
| Hydrant and Access approval | Cleared | 10/19/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 10/19/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 10/20/2020 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/1/2020 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 12/4/2020 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 12/11/2020 | Partial Inspection | JUAN VALENZUELA |
| Green Building Rough | 12/11/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| MERV13>=Rough | 12/11/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 12/11/2020 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2020 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 12/15/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| MERV13>=Rough | 12/15/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2021 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 1/7/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| MERV13>=Rough | 1/7/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 2/17/2021 | Not Ready for Inspection | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2021 | Partial Approval | DAVID HEINE |
| Interior/Exterior Lathing | 3/4/2021 | Not Ready for Inspection | DAVID HEINE |
| Interior/Exterior Lathing | 3/9/2021 | Partial Approval | DAVID HEINE |
| HVAC-Rough | 3/10/2021 | Not Ready for Inspection | DAVID HEINE |
| Rough-Elec/Plmb/HVAC | 3/10/2021 | Partial Approval | DAVID HEINE |
| ELECTRICAL-Rough | 3/12/2021 | Not Ready for Inspection | DAVID HEINE |
| HVAC-Rough | 3/12/2021 | Approved | DAVID HEINE |
| ELECTRICAL-Rough | 3/16/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 3/23/2021 | Corrections Issued | PIERRE VEGA |
| Green Building Rough | 3/23/2021 | Corrections Issued | PIERRE VEGA |
| Insulation | 3/23/2021 | Not Ready for Inspection | PIERRE VEGA |
| MERV13>=Rough | 3/23/2021 | Not Ready for Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 3/25/2021 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 3/25/2021 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 3/25/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| MERV13>=Rough | 3/25/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Insulation | 3/31/2021 | Not Ready for Inspection | PIERRE VEGA |
| Insulation | 4/7/2021 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 4/13/2021 | Partial Approval | PIERRE VEGA |
| Green Building Rough | 4/13/2021 | Not Ready for Inspection | PIERRE VEGA |
| ELECTRICAL-Final | 9/10/2021 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 9/13/2021 | No Access for Inspection | JOHNNY MIRANDA |
| PLUMBING-Final | 9/13/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 9/17/2021 | No Access for Inspection | JOHNNY MIRANDA |
| Drywall Nailing | 9/17/2021 | No Access for Inspection | JOHNNY MIRANDA |
| Final | 9/17/2021 | No Access for Inspection | JOHNNY MIRANDA |
| Green Building Final | 9/17/2021 | No Access for Inspection | JOHNNY MIRANDA |
| Green Building Rough | 9/17/2021 | No Access for Inspection | JOHNNY MIRANDA |
| MERV13>=Final | 9/17/2021 | No Access for Inspection | JOHNNY MIRANDA |
| MERV13>=Rough | 9/17/2021 | No Access for Inspection | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 9/17/2021 | SGSOV Not Ready | JOHNNY MIRANDA |
| Smoke Detectors | 9/17/2021 | No Access for Inspection | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 9/21/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 9/21/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 9/21/2021 | Approved | ENRIQUE MIRELES |
| Final | 9/21/2021 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 9/21/2021 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 9/21/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 9/21/2021 | Approved | ENRIQUE MIRELES |
| MERV13>=Final | 9/21/2021 | Approved | ENRIQUE MIRELES |
| MERV13>=Rough | 9/21/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 9/21/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 9/21/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 9/21/2021 | Approved | ENRIQUE MIRELES |