727 1/2 N HARVARD BLVD 90029
Certificate Information: 727 1/2 N HARVARD BLVD 90029
- Application / Permit
- 20014-20000-03199
- Plan Check / Job No.
- B20VN09902
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 27'-6" X 32' IRREGULAR SHAPE ADDITION & CREATION OF 2ND-FLOOR TO (E) DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d).
- Permit Issued
- Issued on 6/29/2021
- Issuing Office
- Current Status
- CofO Corrected on 9/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2020 | SERGIO MUNIZ |
| Corrections Issued | 8/25/2020 | SERGIO MUNIZ |
| Quality Review Completed | 9/14/2020 | OMID HEDAYAT |
| Applicant returned to address corrections | 10/9/2020 | SERGIO MUNIZ |
| Applicant returned to address corrections | 4/13/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 4/16/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 4/27/2021 | SERGIO MUNIZ |
| Plan Check Approved | 5/18/2021 | SERGIO MUNIZ |
| Building Plans Picked Up | 5/20/2021 | APPLICANT |
| Issued | 6/29/2021 | APPLICANT |
| CofO in Progress | 7/12/2023 | JEFFREY MEAD |
| CofO Issued-Status Void | 7/20/2023 | DEROLD HAUFF |
| Permit Finaled-Status Void | 7/20/2023 | DEROLD HAUFF |
| Re-Activate Permit | 9/13/2023 | DEROLD HAUFF |
| Permit Finaled | 9/26/2023 | DEROLD HAUFF |
| CofO Corrected | 9/26/2023 | DEROLD HAUFF |
| Permit Finaled | 9/26/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2020 | JUAN ASHTON |
| Miscellaneous | Cleared | 10/15/2020 | MAIDEL LUEVANO |
| Address approval | Cleared | 10/23/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 10/26/2020 | JUAN ASHTON |
| Low Impact Development | Cleared | 3/24/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/24/2021 | JEANIE LAM |
Contact Information
| Contractor | Beresheet Construction & Design Inc; Lic. No.: 1057051-B | 8362 1/2 WEST 3RD STREET LOS ANGELES, CA 90048 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/12/2021 | Partial Inspection | CHARLES BOGHOSKHAN |
| Sewer | 7/12/2021 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Underground Mechanical | 7/12/2021 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Deputy Drilled-In Anchors | 7/13/2021 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 7/30/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Pre-Inspection | 7/30/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Sewer | 7/30/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 8/13/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Rough | 8/13/2021 | Partial Approval | ARTHUR SARGSYAN |
| Pre-Inspection | 8/13/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 8/18/2021 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 8/18/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 9/15/2021 | Partial Approval | ARTHUR SARGSYAN |
| Green Building Rough | 9/15/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| MERV13>=Rough | 9/15/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 9/28/2021 | Partial Approval | ARTHUR SARGSYAN |
| Green Building Rough | 9/28/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| MERV13>=Rough | 9/28/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 10/25/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 10/25/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 10/25/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 10/25/2021 | Approved | ARTHUR SARGSYAN |
| MERV13>=Rough | 10/25/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 10/25/2021 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 10/25/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 11/18/2021 | Approved | MASHEL JONGERT |
| Insulation | 11/18/2021 | Approved | MASHEL JONGERT |
| Interior/Exterior Lathing | 11/18/2021 | Conditional Approval | MASHEL JONGERT |
| Shower Pan | 11/18/2021 | Approved | MASHEL JONGERT |
| Drywall Nailing | 12/3/2021 | Approved | MASHEL JONGERT |
| Interior/Exterior Lathing | 12/3/2021 | Approved | MASHEL JONGERT |
| Shower Pan | 12/3/2021 | Approved | MASHEL JONGERT |
| Interior/Exterior Lathing | 2/10/2022 | Approved | JOSEPH MCGARRY |
| Gas Test | 4/29/2022 | Approved | SHAVONNE ESPINOZA |
| Sewer | 4/29/2022 | Approved | SHAVONNE ESPINOZA |
| Underground Mechanical | 4/29/2022 | Approved | SHAVONNE ESPINOZA |
| Pre-Inspection | 5/4/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 12/22/2022 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 12/22/2022 | Corrections Issued | JEFFREY MEAD |
| ELECTRICAL-Final | 4/20/2023 | Approved | JEFFREY MEAD |
| Final | 4/20/2023 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 4/20/2023 | Approved | JEFFREY MEAD |
| HVAC-Final | 4/20/2023 | Approved | JEFFREY MEAD |
| MERV13>=Final | 4/20/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 4/20/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 4/20/2023 | SGSOV Not Ready | JEFFREY MEAD |
| Service/Power Release | 4/20/2023 | Approved | JEFFREY MEAD |
| Smoke Detectors | 4/20/2023 | Approved | JEFFREY MEAD |
| Final | 6/20/2023 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 6/20/2023 | SGSOV Not Ready | JEFFREY MEAD |
| Final | 7/11/2023 | OK to Issue CofO | JEFFREY MEAD |
| Gas Test | 7/11/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 7/11/2023 | SGSOV Approved | JEFFREY MEAD |