7765 N SHADYSPRING DR 91504

Certificate Information: 7765 N SHADYSPRING DR 91504

Application / Permit
20014-20000-03198
Plan Check / Job No.
B20VN09898
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 19'-4" x 9'-6" ADDITION TO THE REAR OF THE (E) SINGLE FAMILY DWELLING, CONVERT 6'-1" x 5'-4" OF THE (E)PORCH TO LIVING ROOM AND 10'-1" x 6'-3" PORTION OF THE (E) GARAGE INTO A (N) BATHROOM . ADD 10'-1" x 6'-0" TO (E) ONE CAR GARAGE AND 6'-6" x 2'-6" OF PORCH TO (E) SINGLE FAMILY DWELLING.
Permit Issued
Issued on 9/23/2020
Issuing Office
Current Status
CofO Issued on 7/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2020 APPLICANT
Assigned to Plan Check Engineer 8/5/2020 SARKIS HARABEDIAN
Corrections Issued 8/5/2020 SARKIS HARABEDIAN
Plan Check Approved 9/23/2020 SARKIS HARABEDIAN
Issued 9/23/2020 APPLICANT
CofO in Progress 4/14/2021 BEAU COLLINS
Permit Finaled 7/24/2021 MICHAEL SMITH
CofO Issued 7/24/2021 MICHAEL SMITH
Permit Finaled 7/24/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/31/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 8/31/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 8/31/2020 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 9/4/2020 BARTON HOLMES

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/27/2020 Partial Approval BEAU COLLINS
Footing/Foundation/Slab 10/30/2020 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 11/18/2020 Corrections Issued BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 11/24/2020 Approved BEAU COLLINS
BUILDING-Rough-Frame 12/14/2020 Partial Approval BEAU COLLINS
ELECTRICAL-Rough 12/14/2020 Approved BEAU COLLINS
Green Building Rough 12/14/2020 Not Ready for Inspection BEAU COLLINS
HVAC-Rough 12/14/2020 Approved BEAU COLLINS
MERV13>=Rough 12/14/2020 Approved BEAU COLLINS
PLUMBING-Rough 12/14/2020 Partial Approval BEAU COLLINS
Interior/Exterior Lathing 12/22/2020 Approved MATTHEW NELSON
Wood Frame 12/28/2020 Conditional Approval BEAU COLLINS
Insulation 12/31/2020 Approved MATTHEW NELSON
Shower Pan 12/31/2020 Approved MATTHEW NELSON
Drywall Nailing 1/5/2021 Approved MATTHEW NELSON
Green Building Rough 1/5/2021 Approved MATTHEW NELSON
Interior/Exterior Lathing 1/14/2021 Approved BEAU COLLINS
BUILDING-Rough-Frame 3/25/2021 Approved BEAU COLLINS
Final 3/25/2021 Corrections Issued BEAU COLLINS
Green Building Final 3/25/2021 Not Ready for Inspection BEAU COLLINS
MERV13>=Final 3/25/2021 Not Ready for Inspection BEAU COLLINS
SGSOV-Seismic Gas S/O Valve 3/25/2021 SGSOV Not Ready BEAU COLLINS
Smoke Detectors 3/25/2021 Approved BEAU COLLINS
Final 4/13/2021 OK to Issue CofO BEAU COLLINS
Green Building Final 4/13/2021 Approved BEAU COLLINS
MERV13>=Final 4/13/2021 Approved BEAU COLLINS
SGSOV-Seismic Gas S/O Valve 4/13/2021 SGSOV Approved BEAU COLLINS