7765 N SHADYSPRING DR 91504
Certificate Information: 7765 N SHADYSPRING DR 91504
- Application / Permit
- 20014-20000-03198
- Plan Check / Job No.
- B20VN09898
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 19'-4" x 9'-6" ADDITION TO THE REAR OF THE (E) SINGLE FAMILY DWELLING, CONVERT 6'-1" x 5'-4" OF THE (E)PORCH TO LIVING ROOM AND 10'-1" x 6'-3" PORTION OF THE (E) GARAGE INTO A (N) BATHROOM . ADD 10'-1" x 6'-0" TO (E) ONE CAR GARAGE AND 6'-6" x 2'-6" OF PORCH TO (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 9/23/2020
- Issuing Office
- Current Status
- CofO Issued on 7/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2020 | SARKIS HARABEDIAN |
| Corrections Issued | 8/5/2020 | SARKIS HARABEDIAN |
| Plan Check Approved | 9/23/2020 | SARKIS HARABEDIAN |
| Issued | 9/23/2020 | APPLICANT |
| CofO in Progress | 4/14/2021 | BEAU COLLINS |
| Permit Finaled | 7/24/2021 | MICHAEL SMITH |
| CofO Issued | 7/24/2021 | MICHAEL SMITH |
| Permit Finaled | 7/24/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 8/31/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 8/31/2020 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 9/4/2020 | BARTON HOLMES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/27/2020 | Partial Approval | BEAU COLLINS |
| Footing/Foundation/Slab | 10/30/2020 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2020 | Corrections Issued | BEAU COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2020 | Approved | BEAU COLLINS |
| BUILDING-Rough-Frame | 12/14/2020 | Partial Approval | BEAU COLLINS |
| ELECTRICAL-Rough | 12/14/2020 | Approved | BEAU COLLINS |
| Green Building Rough | 12/14/2020 | Not Ready for Inspection | BEAU COLLINS |
| HVAC-Rough | 12/14/2020 | Approved | BEAU COLLINS |
| MERV13>=Rough | 12/14/2020 | Approved | BEAU COLLINS |
| PLUMBING-Rough | 12/14/2020 | Partial Approval | BEAU COLLINS |
| Interior/Exterior Lathing | 12/22/2020 | Approved | MATTHEW NELSON |
| Wood Frame | 12/28/2020 | Conditional Approval | BEAU COLLINS |
| Insulation | 12/31/2020 | Approved | MATTHEW NELSON |
| Shower Pan | 12/31/2020 | Approved | MATTHEW NELSON |
| Drywall Nailing | 1/5/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 1/5/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 1/14/2021 | Approved | BEAU COLLINS |
| BUILDING-Rough-Frame | 3/25/2021 | Approved | BEAU COLLINS |
| Final | 3/25/2021 | Corrections Issued | BEAU COLLINS |
| Green Building Final | 3/25/2021 | Not Ready for Inspection | BEAU COLLINS |
| MERV13>=Final | 3/25/2021 | Not Ready for Inspection | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 3/25/2021 | SGSOV Not Ready | BEAU COLLINS |
| Smoke Detectors | 3/25/2021 | Approved | BEAU COLLINS |
| Final | 4/13/2021 | OK to Issue CofO | BEAU COLLINS |
| Green Building Final | 4/13/2021 | Approved | BEAU COLLINS |
| MERV13>=Final | 4/13/2021 | Approved | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 4/13/2021 | SGSOV Approved | BEAU COLLINS |