5651 N RANCHITO AVE 91401

Certificate Information: 5651 N RANCHITO AVE 91401

Application / Permit
20014-20000-03194
Plan Check / Job No.
B20VN09885
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL. 3'-11" X 10'-1" 1ST-FLOOR ADDITION & CREATE 26'-1" X 25'-9" 2ND-FLOOR TO (E) SINGLE FAMILY DWELLING. ENCLOSE FRONT PORCH AND CONVERT TO LIVABLE SPACE. FIRE SPRINKLER REQUIRED NFPA-13D.
Permit Issued
Issued on 3/4/2021
Issuing Office
Current Status
CofO Issued on 4/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 SERGIO MUNIZ
Corrections Issued 8/28/2020 SERGIO MUNIZ
Quality Review Completed 9/21/2020 OMID HEDAYAT
Plan Check Approved 3/2/2021 SERGIO MUNIZ
Issued 3/4/2021 APPLICANT
Building Plans Picked Up 3/5/2021 APPLICANT
CofO in Progress 10/31/2022 RICHARD DOCKUS
Permit Finaled 4/1/2023 DANIEL ORRANTE
CofO Issued 4/1/2023 DANIEL ORRANTE
Permit Finaled 4/1/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/19/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 10/19/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 12/30/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 12/31/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/8/2021 Conditional Approval MISAEL ESPARZA
Footing/Foundation/Slab 4/12/2021 Approved JENNIFER RABUCHIN
PLUMBING-Rough 4/12/2021 Partial Approval JENNIFER RABUCHIN
Sewer 4/12/2021 Approved JENNIFER RABUCHIN
Special/Order Compliance 4/12/2021 Corrections Issued JENNIFER RABUCHIN
Insulation 4/21/2021 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 5/19/2021 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/19/2021 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/27/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 5/27/2021 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/27/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 5/27/2021 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 5/27/2021 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 6/7/2021 Partial Approval ALAN MORELOS
Shower Pan 6/18/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/24/2021 Approved ALAN MORELOS
Insulation 6/30/2021 Corrections Issued ALAN MORELOS
Insulation 7/12/2021 Partial Inspection DEANDRE HOFFMAN
Insulation 7/19/2021 Approved JAVIER RAMOS JR
Drywall Nailing 7/27/2021 Not Ready for Inspection WILLIAM WREN
Green Building Rough 7/27/2021 Corrections Issued AMY COLIN
ELECTRICAL-Final 7/20/2022 Approved RICHARD DOCKUS
PLUMBING-Final 7/20/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 7/22/2022 Approved RICHARD DOCKUS
Drywall Nailing 7/22/2022 Approved RICHARD DOCKUS
Green Building Final 7/22/2022 Approved RICHARD DOCKUS
Green Building Rough 7/22/2022 Approved RICHARD DOCKUS
HVAC-Final 7/22/2022 Corrections Issued RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 7/22/2022 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 7/22/2022 Approved RICHARD DOCKUS
ELECTRICAL-Final 7/26/2022 Corrections Issued JACK KARGODORIAN
HVAC-Final 7/26/2022 Not Ready for Inspection JACK KARGODORIAN
Final 7/28/2022 Not Ready for Inspection JACK KARGODORIAN
Gas Test 7/28/2022 Approved JACK KARGODORIAN
Service/Power Release 7/28/2022 Not Ready for Inspection JACK KARGODORIAN
Final 8/3/2022 Not Ready for Inspection RICHARD DOCKUS
Final 8/16/2022 Partial Approval JENNIFER RABUCHIN
HVAC-Final 8/16/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/27/2022 Approved RICHARD DOCKUS
Final 10/28/2022 OK to Issue CofO RICHARD DOCKUS
Service/Power Release 10/28/2022 Not Required RICHARD DOCKUS
Service/Power Release 11/2/2022 Approved RICHARD DOCKUS