5651 N RANCHITO AVE 91401
Certificate Information: 5651 N RANCHITO AVE 91401
- Application / Permit
- 20014-20000-03194
- Plan Check / Job No.
- B20VN09885
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL. 3'-11" X 10'-1" 1ST-FLOOR ADDITION & CREATE 26'-1" X 25'-9" 2ND-FLOOR TO (E) SINGLE FAMILY DWELLING. ENCLOSE FRONT PORCH AND CONVERT TO LIVABLE SPACE. FIRE SPRINKLER REQUIRED NFPA-13D.
- Permit Issued
- Issued on 3/4/2021
- Issuing Office
- Current Status
- CofO Issued on 4/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2020 | SERGIO MUNIZ |
| Corrections Issued | 8/28/2020 | SERGIO MUNIZ |
| Quality Review Completed | 9/21/2020 | OMID HEDAYAT |
| Plan Check Approved | 3/2/2021 | SERGIO MUNIZ |
| Issued | 3/4/2021 | APPLICANT |
| Building Plans Picked Up | 3/5/2021 | APPLICANT |
| CofO in Progress | 10/31/2022 | RICHARD DOCKUS |
| Permit Finaled | 4/1/2023 | DANIEL ORRANTE |
| CofO Issued | 4/1/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/1/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 10/19/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 12/30/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/31/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/8/2021 | Conditional Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/12/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/12/2021 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 4/12/2021 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 4/12/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 4/21/2021 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 5/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/27/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/27/2021 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 5/27/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/27/2021 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/7/2021 | Partial Approval | ALAN MORELOS |
| Shower Pan | 6/18/2021 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/24/2021 | Approved | ALAN MORELOS |
| Insulation | 6/30/2021 | Corrections Issued | ALAN MORELOS |
| Insulation | 7/12/2021 | Partial Inspection | DEANDRE HOFFMAN |
| Insulation | 7/19/2021 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 7/27/2021 | Not Ready for Inspection | WILLIAM WREN |
| Green Building Rough | 7/27/2021 | Corrections Issued | AMY COLIN |
| ELECTRICAL-Final | 7/20/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 7/20/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 7/22/2022 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 7/22/2022 | Approved | RICHARD DOCKUS |
| Green Building Final | 7/22/2022 | Approved | RICHARD DOCKUS |
| Green Building Rough | 7/22/2022 | Approved | RICHARD DOCKUS |
| HVAC-Final | 7/22/2022 | Corrections Issued | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 7/22/2022 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 7/22/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 7/26/2022 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Final | 7/26/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 7/28/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Gas Test | 7/28/2022 | Approved | JACK KARGODORIAN |
| Service/Power Release | 7/28/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 8/3/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 8/16/2022 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Final | 8/16/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/27/2022 | Approved | RICHARD DOCKUS |
| Final | 10/28/2022 | OK to Issue CofO | RICHARD DOCKUS |
| Service/Power Release | 10/28/2022 | Not Required | RICHARD DOCKUS |
| Service/Power Release | 11/2/2022 | Approved | RICHARD DOCKUS |