6576 S 3RD AVE 90043
Certificate Information: 6576 S 3RD AVE 90043
- Application / Permit
- 20014-20000-03180
- Plan Check / Job No.
- B20VN09834
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 7'-3" x 10'-0" AND 9'-5" x 6'-3" IRREG. SHAPED ADDITION TO THE REAR OF THE (E) SINGLE FAMILY DWELLING INTERIOR REMODEL TO RAISE FLOOR AND CEILING AT THE PROPOSED MASTER BEDROOM AND BATHROOM AND RE-ROOF.
- Permit Issued
- Issued on 9/9/2020
- Issuing Office
- Current Status
- CofO Issued on 9/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2020 | SARKIS HARABEDIAN |
| Corrections Issued | 8/5/2020 | SARKIS HARABEDIAN |
| Plan Check Approved | 9/1/2020 | SARKIS HARABEDIAN |
| Issued | 9/9/2020 | APPLICANT |
| CofO in Progress | 8/30/2021 | FREDDIE RIVERA |
| CofO Issued | 9/2/2021 | DEROLD HAUFF |
| Permit Finaled | 9/2/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2020 | ELENA LOPEZ |
| Roof/Waste drainage to street | Cleared | 8/11/2020 | ELENA LOPEZ |
| Sewer availability | Cleared | 8/11/2020 | ELENA LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Medina,, Armando; Lic. No.: C83911 | 121 N VAIL AVE MONTEBELLO, CA 90640 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/15/2020 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 10/14/2020 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 10/14/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 10/14/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 11/19/2020 | Partial Approval | FREDDIE RIVERA |
| Wood Frame | 11/19/2020 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2020 | Partial Approval | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 12/3/2020 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 1/4/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2021 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 1/4/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 1/4/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 1/4/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 1/13/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 1/13/2021 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 1/13/2021 | Corrections Issued | FREDDIE RIVERA |
| Insulation | 1/14/2021 | Corrections Issued | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 1/21/2021 | Corrections Issued | FREDDIE RIVERA |
| Interior/Exterior Lathing | 2/1/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Final | 2/1/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Insulation | 2/17/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 2/17/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 2/17/2021 | Corrections Issued | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 2/24/2021 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/3/2021 | Conditional Approval | FREDDIE RIVERA |
| Insulation | 3/3/2021 | Approved | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 3/3/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/12/2021 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 3/12/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 3/12/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 3/12/2021 | Approved | FREDDIE RIVERA |
| Final | 6/9/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/9/2021 | Approved | EUGENE CASSIDY |
| Green Building Final | 6/9/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 6/9/2021 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 6/9/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 7/16/2021 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 7/16/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Smoke Detectors | 7/16/2021 | Approved | FREDDIE RIVERA |
| Final | 7/26/2021 | OK to Issue CofO | FREDDIE RIVERA |
| Green Building Final | 7/26/2021 | Approved | FREDDIE RIVERA |
| Final | 9/1/2021 | No Access for Inspection | FREDDIE RIVERA |