9771 W DONINGTON PL 90210
Certificate Information: 9771 W DONINGTON PL 90210
- Application / Permit
- 20014-20000-03178
- Plan Check / Job No.
- B20VN09831
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 24'-6" X 19'-6" ADDITION TO (E ) 2-STORY SINGLE FAMILY DWELLING, ENCLOSE (E) COVERED PORCH AND INTERIOR REMODEL.
- Permit Issued
- Issued on 3/5/2021
- Issuing Office
- Current Status
- CofO Issued on 11/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2020 | SERGIO MUNIZ |
| Corrections Issued | 8/24/2020 | SERGIO MUNIZ |
| Quality Review Completed | 9/17/2020 | OMID HEDAYAT |
| Plan Check Approved | 2/11/2021 | SERGIO MUNIZ |
| Issued | 3/5/2021 | APPLICANT |
| Building Plans Picked Up | 3/9/2021 | APPLICANT |
| CofO in Progress | 11/10/2025 | SEAN HAUPT |
| Permit Finaled | 11/13/2025 | RICHARD STEINBACH |
| CofO Issued | 11/13/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/13/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| ZA Case | Cleared | 10/14/2020 | ANACANY HURTADO |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2020 | NIKTA MOUSAVI |
| Roof/Waste drainage to street | Cleared | 10/29/2020 | NIKTA MOUSAVI |
| Hydrant and Access approval | Cleared | 11/16/2020 | MATTHEW CRAIG |
| Specific Plan | Cleared | 1/12/2021 | LIZZI BEDUYA |
| Grading Pre-Inspection | Cleared | 2/5/2021 | SERGIO MUNIZ |
Contact Information
| Contractor | Cuchumbos; Lic. No.: 729949-B | 8975 TELFAIR AVENUE SUN VALLEY, CA 91352 |
| Engineer | Jamil,, Bashar S; Lic. No.: C83129 | 751 SHASTA DR CORONA, CA 92881 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/25/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Deputy Reinf. Concrete | 4/16/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Deputy Wood Construction | 6/7/2021 | Conditional Approval | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 6/23/2021 | Corrections Issued | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 6/23/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Green Building Rough | 6/23/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Underground Mechanical | 6/23/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 6/25/2021 | Conditional Approval | CHRISTOPHER WILSON |
| Gas Test | 6/25/2021 | Partial Approval | CHRISTOPHER WILSON |
| Green Building Rough | 6/25/2021 | Approved | CHRISTOPHER WILSON |
| Insulation | 6/29/2021 | Approved | ANTHONY MCDOWALL |
| Drywall Nailing | 7/6/2021 | Approved | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 12/10/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 12/10/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 12/10/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Green Building Final | 12/10/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 12/10/2021 | SGSOV Approved | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 12/10/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 12/16/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 12/16/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Green Building Final | 12/16/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 12/16/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Final | 11/7/2025 | OK to Issue CofO | SEAN HAUPT |
| Footing/Foundation/Slab | 11/7/2025 | Approved | SEAN HAUPT |
| Green Building Final | 11/7/2025 | Approved | SEAN HAUPT |
| Smoke Detectors | 11/7/2025 | Approved | SEAN HAUPT |