431 1/2 W 78TH ST 90003
Certificate Information: 431 1/2 W 78TH ST 90003
- Application / Permit
- 20014-20000-03177
- Plan Check / Job No.
- B20VN09830
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 26'-5.5" x 13'-10" ADDITION TO AND CONVERT THE (E)DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d).
- Permit Issued
- Issued on 9/14/2020
- Issuing Office
- Current Status
- CofO Issued on 12/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2020 | SARKIS HARABEDIAN |
| Corrections Issued | 8/4/2020 | SARKIS HARABEDIAN |
| Plan Check Approved | 9/8/2020 | SARKIS HARABEDIAN |
| Issued | 9/14/2020 | APPLICANT |
| CofO in Progress | 10/18/2021 | ANTHONY EGSON |
| Permit Finaled | 12/17/2021 | DEROLD HAUFF |
| CofO Issued | 12/17/2021 | DEROLD HAUFF |
| Permit Finaled | 12/17/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/17/2020 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 8/17/2020 | WALLIE JONG |
| Sewer availability | Cleared | 8/17/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2020 | WALLIE JONG |
| Hold | Cleared | 2/17/2021 | JASON SHEETS |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 2/24/2021 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 3/3/2021 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 3/3/2021 | Off-Hour Fees Due | |
| BUILDING-Rough-Frame | 3/15/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Gas Test | 3/15/2021 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 3/15/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| MERV13>=Rough | 3/15/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 3/26/2021 | Corrections Issued | DAVID FEILER |
| Gas Test | 3/26/2021 | Partial Approval | DAVID FEILER |
| Sewer | 3/26/2021 | Approved | DAVID FEILER |
| Underground Mechanical | 3/26/2021 | Approved | DAVID FEILER |
| Wood Frame | 3/26/2021 | Corrections Issued | DAVID FEILER |
| BUILDING-Rough-Frame | 4/17/2021 | Conditional Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 4/17/2021 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2021 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 4/17/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 4/17/2021 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 4/17/2021 | Approved | JOSEPH MCGARRY |
| Insulation | 4/29/2021 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/29/2021 | Partial Approval | SABAS ALONSO |
| Drywall Nailing | 5/4/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 5/4/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 5/4/2021 | Off-Hour Fees Due | |
| Shower Pan | 5/4/2021 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 5/12/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 5/12/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/2/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 8/2/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 8/2/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/2/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 8/2/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| MERV13>=Rough | 8/2/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/2/2021 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 8/2/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/4/2021 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 8/4/2021 | Approved | FREDDIE RIVERA |
| Final | 8/4/2021 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 8/4/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| MERV13>=Final | 8/4/2021 | Approved | FREDDIE RIVERA |
| MERV13>=Rough | 8/4/2021 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 8/4/2021 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 8/4/2021 | Approved | FREDDIE RIVERA |
| Final | 9/9/2021 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 9/9/2021 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/9/2021 | SGSOV Approved | SABAS ALONSO |
| Final | 9/24/2021 | Corrections Issued | SABAS ALONSO |
| Final | 9/29/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 10/4/2021 | Corrections Issued | EUGENE CASSIDY |
| Final | 10/15/2021 | OK to Issue CofO | ANTHONY EGSON |