8411 N CASABA AVE 91306

Certificate Information: 8411 N CASABA AVE 91306

Application / Permit
20014-20000-03176
Plan Check / Job No.
B20VN09819
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 12'-3" x 9'-7" PATIO COVER AND CONVERT THE DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). ALL WORK PER ENGINEER.
Permit Issued
Issued on 2/22/2022
Issuing Office
Current Status
CofO Issued on 1/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2020 APPLICANT
Assigned to Plan Check Engineer 8/29/2020 AMIR DANAI
Corrections Issued 9/1/2020 AMIR DANAI
Plan Check Approved 10/28/2020 ANGELICA MARTINEZ
Issued 2/22/2022 APPLICANT
CofO in Progress 1/12/2023 CHRIS CHRISTENSEN
CofO Issued 1/19/2023 JOHN JANSON
Permit Finaled 1/19/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/2/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 10/2/2020 ADRIAN CASTRO
Sewer availability Cleared 10/2/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/7/2020 ADRIAN CASTRO

Contact Information

Contractor Ind Construction Llc; Lic. No.: 937833-B 16430 VENTURA BLVD STE 208      ENCINO, CA 91436
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/13/2022 Approved CHRIS CHRISTENSEN
Pre-Inspection 7/11/2022 Approved CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 7/21/2022 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 7/25/2022 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 9/13/2022 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/3/2022 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/3/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 10/3/2022 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 10/3/2022 Approved CHRIS CHRISTENSEN
Insulation 10/3/2022 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 10/3/2022 Approved CHRIS CHRISTENSEN
Wood Frame 10/3/2022 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/11/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 10/11/2022 Approved CHRIS CHRISTENSEN
Insulation 10/11/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/11/2022 Partial Approval CHRIS CHRISTENSEN
Insulation 10/12/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/12/2022 Approved CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 10/12/2022 Approved CHRIS CHRISTENSEN
Wood Frame 10/12/2022 Approved CHRIS CHRISTENSEN
Drywall Nailing 10/21/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 10/21/2022 Partial Inspection JUSTIN HAWLEY
Shower Pan 10/21/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 10/31/2022 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Final 12/15/2022 Approved KRISTEN CAUSEY
Final 12/15/2022 Corrections Issued KRISTEN CAUSEY
Green Building Final 12/15/2022 Not Ready for Inspection KRISTEN CAUSEY
HVAC-Final 12/15/2022 Not Ready for Inspection KRISTEN CAUSEY
PLUMBING-Final 12/15/2022 Approved KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 12/15/2022 SGSOV Approved KRISTEN CAUSEY
Smoke Detectors 12/15/2022 Approved KRISTEN CAUSEY
ELECTRICAL-Final 1/3/2023 Not Ready for Inspection KRISTEN CAUSEY
Final 1/3/2023 Not Ready for Inspection KRISTEN CAUSEY
Green Building Final 1/3/2023 Not Ready for Inspection KRISTEN CAUSEY
HVAC-Final 1/3/2023 Not Ready for Inspection KRISTEN CAUSEY
PLUMBING-Final 1/3/2023 Not Ready for Inspection KRISTEN CAUSEY
ELECTRICAL-Final 1/5/2023 Not Ready for Inspection KRISTEN CAUSEY
HVAC-Final 1/5/2023 Not Ready for Inspection KRISTEN CAUSEY
PLUMBING-Final 1/5/2023 Not Ready for Inspection KRISTEN CAUSEY
Final 1/11/2023 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 1/11/2023 Approved CHRIS CHRISTENSEN