8411 N CASABA AVE 91306
Certificate Information: 8411 N CASABA AVE 91306
- Application / Permit
- 20014-20000-03176
- Plan Check / Job No.
- B20VN09819
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 12'-3" x 9'-7" PATIO COVER AND CONVERT THE DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 2/22/2022
- Issuing Office
- Current Status
- CofO Issued on 1/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2020 | AMIR DANAI |
| Corrections Issued | 9/1/2020 | AMIR DANAI |
| Plan Check Approved | 10/28/2020 | ANGELICA MARTINEZ |
| Issued | 2/22/2022 | APPLICANT |
| CofO in Progress | 1/12/2023 | CHRIS CHRISTENSEN |
| CofO Issued | 1/19/2023 | JOHN JANSON |
| Permit Finaled | 1/19/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/2/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 10/2/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 10/2/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Ind Construction Llc; Lic. No.: 937833-B | 16430 VENTURA BLVD STE 208 ENCINO, CA 91436 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/13/2022 | Approved | CHRIS CHRISTENSEN |
| Pre-Inspection | 7/11/2022 | Approved | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 7/21/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 7/25/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 9/13/2022 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/3/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 10/3/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 10/3/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 10/3/2022 | Approved | CHRIS CHRISTENSEN |
| Insulation | 10/3/2022 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/3/2022 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 10/3/2022 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/11/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 10/11/2022 | Approved | CHRIS CHRISTENSEN |
| Insulation | 10/11/2022 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 10/11/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 10/12/2022 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 10/12/2022 | Approved | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 10/12/2022 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 10/12/2022 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 10/21/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 10/21/2022 | Partial Inspection | JUSTIN HAWLEY |
| Shower Pan | 10/21/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 10/31/2022 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 12/15/2022 | Approved | KRISTEN CAUSEY |
| Final | 12/15/2022 | Corrections Issued | KRISTEN CAUSEY |
| Green Building Final | 12/15/2022 | Not Ready for Inspection | KRISTEN CAUSEY |
| HVAC-Final | 12/15/2022 | Not Ready for Inspection | KRISTEN CAUSEY |
| PLUMBING-Final | 12/15/2022 | Approved | KRISTEN CAUSEY |
| SGSOV-Seismic Gas S/O Valve | 12/15/2022 | SGSOV Approved | KRISTEN CAUSEY |
| Smoke Detectors | 12/15/2022 | Approved | KRISTEN CAUSEY |
| ELECTRICAL-Final | 1/3/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| Final | 1/3/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| Green Building Final | 1/3/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| HVAC-Final | 1/3/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| PLUMBING-Final | 1/3/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| ELECTRICAL-Final | 1/5/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| HVAC-Final | 1/5/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| PLUMBING-Final | 1/5/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| Final | 1/11/2023 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 1/11/2023 | Approved | CHRIS CHRISTENSEN |